What is NEC option A?
Fully priced activity schedule
Why was NEC Option A used?
-Cost Certainty
-Design control
-Collaborative working
What was the client objectives?
The client’s priority was to complete all demolition, and civils works by the end of 2024, enabling construction of the new production line in 2025 and wing production by 2026.
What is a compensation event?
An event which does not arise from the contractor but the contractor is due additional cost and programme.
What clause relates to CEs?
Clause 60
Clause 61 – Notification of compensation events.
Clause 62 – Submission of quotations for compensation events.
Clause 63 – Assessment of compensation events.
Clause 64 – Project Manager’s assessment if the contractor fails to submit.
CE Timeline?
Whats was the value of the initial project and then the overall total?
-Jig demo - £398k
-Total - £2.4m
How were you given delegated authority?
What was your role in the project?
-Delegated authority role (14.2)
- Not recognised under NEC but a traditional QS role
-Assessment and certification of interim payments,
-Evaluation of compensation events
-Commercial review of contractor proposals
What challenges were there to achieving VFM?
-No Competitive Tendering
-Incomplete Design
-Unknown Site Conditions
What is contract negotiation?
Contract negotiation is the process of discussing, adjusting, and agreeing on the terms and conditions of a contract between two or more parties
Advantages of contract negotiation?
-Quicker start on site
-Continued relationship
-Risk management
-Collaboration &transparency
Disadvantages of contract negotiation?
-Commercial risk - non comp + CEs
-Design risk
Advantages of delaying the project?
-Comp tender and cost assurance
-Reduced design risk
-Risk management
-Budget and funding alignment
-Stakeholder engagement
Disadvantages of delaying the project?
-Delay programme and miss key date
-Unlikely that a full design would have been possible due to unknown conditions
-Market condition changes
What option was pursued?
Contract negotiation
What is collaboration?
Working together toward a shared goal, where individuals or organizations contribute their skills, knowledge, and resources to achieve better outcomes than they could alone.
How did you demonstrate value for money?
-Open tendering
-Multiple subcontractors approached.
-Close discussion with contractor
-Benchmark
How did you ensure competitive pricing?
-Open tendering
-Multiple subcontractors approached.
How would you change the project if you were to do it again?
-Earlier client engagement understanding their master plan to allow competitive tendering practices
- 2 stage dnb approach
What procurement route was used?
Traditional
Why use a traditional procurement approach?
-Cost certainty
-Competitive pricing
-Design control
Why wouldn’t you use a traditional procurement approach?
-Time consuming
-No contractor input
-Lack of flexibility
What is NEC option E
Cost Reimbursable Contract