Contract Admin - SOS Flashcards

(23 cards)

1
Q

What is the role of a Contract Administrator (CA) in a construction project?

A

-Managing the contract between the employer and the contractor once the contract is signed.
- Issuing instructions, certifying payments, assessing extensions of time, and ensuring that the contract terms are followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How should a Contract Administrator act?

A

Impartially and fairly, even though they are appointed by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is practical completion?

A

-The works are complete except for minor defects that do not prevent the building from being used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is sectional completion?

A
  • Allows different parts of the project to be completed and handed over at different times, each with its own completion date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is partial possession?

A

-The client takes possession of part of the works before overall completion, which can affect liability and insurance provisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract Administrators main responsibilities?

A

-Certifying Payment
-Instructions
-Monitor progress
-EOTs
-Communication
-CDM compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What role have you acted in within your projects?

A

Appointed delegated authority role under the PM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EOT process under JCT?

A

-EOT can be claimed if a delay is caused by a Relevant Event
-Notification by the Contractor
-Assessment by the Contract Administrator
-Impact on Liquidated Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a payment notice?

A

A payment notice is a formal document issued in construction contracts to notify the amount due for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is payment noticed used?

A

-Legal Compliance
-Dispute prevention
-Supports interim valuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What forms a payment notice?

A

-The amount due for payment
-The basis of the calculation
-The due date and payment period
-The payer and payee details
-A reference to the contract or valuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you describe your involvement in managing defects under the contract?

A

At the end of the 12-month defects period, I issued a notice of making good defects and confirmed that all remedial works were completed satisfactorily. Following this, I released the remaining retention held on the scheme. This process was carried out in accordance with the NEC3 contract provisions and ensured the client’s interests were protected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How are defects manged under the NEC

A

-You’ve issued a notice of making good defects at the end of the 12-month period.
-You’ve released retention after confirming defects were resolved.
-issue correction of defects
-Final defects cert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What guidance is there for CA?

A

I am aware of the RICS Contract Administration guidance note which outlines the responsibilities and impartiality required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why is impartiality important for a Contract Administrator

A

Impartiality ensures fair treatment of all parties and upholds the integrity of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did you ensure impartiality while administering the contract?

A

I followed RICS guidance and contract terms, treating all parties fairly and documenting decisions.

17
Q

What’s the purpose of the defect’s liability period?

A

-Quality assurance
-Rectification of defects

18
Q

How long does the defect liability typically run for, and why

A

-12 months
-A full year to test weather performance
-Sufficient time for defects to manifest
-Reasonable time to rectify issues

19
Q

How are liquidated damages calculated?

A

-Calculated on actually loss expressed daily or weekly

20
Q

What is the process for deducting LADS?

A

-Issue notification of intention of LADS
-Apply deduction to payment cert
-Record in payment cert

21
Q

Describe how you managed the change control procedure under Clause 14.2 on the SAYTS Paintshop project

A

-Adhered with the strict timelines in the contract
-Enforced the use of PMI, EWN & CE mech
- Reviewed CE price against the schedule of cost components and 60.1
-Utilised SYPRO for clear change control

22
Q

What does A CA do 1 month prior to PC?

A

-Snagging prep
-Building Control sign‑offs / final inspections
-Fire Officer sign‑offs
-Chase warranties

23
Q

Contract Administrator (CA) vs Employer’s Agent (EA)?

A

-CA not included in DNB
-To administer the contract impartially between Employer and Contractor.

-EA inc in DNB
-To act on behalf of the Employer as their representative and project interface.