Case study Flashcards

(59 cards)

1
Q

Were other value engineering items discussed?

A

Yes, so I proposed other options, which the client did not wish to move forward with, for example, I proposed changing the specification of the ironmongery & faceplates throughout the property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Were other scope reduction items discussed?

A

Yes, other options which were not approved include
- Reducing the scope of the Audio Visual package by removing the speaker system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you estimate the costs of the VE & Scope reduction items?

A

For some items, such as the polished plaster to paint change, I had tendered rates for both items. Therefore, I undertook an add & omit exercise for this item.

For other items, I looked to market testing, such as for the change in timber flooring, I reached out to the subcontractor to provide an updated quotation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When you did the add & omit exercise for the VE options, did you consider any other costs?

A

Yes, I also included within the saving the OH&P adjustment using the contractor’s tendered rate.

I also adjusted sub-contractor preliminaries in terms of the reduction in stone.

I also considered potential programme savings from the options, however, I felt this was unlikely to be achieved and confirmed this after liaising with the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you ensure things like the timber change were adequate for the client?

A

Firstly, the timber proposed was one that myself and the architect had used on previous projects, for which we had good experiences.

The architect also ordered samples for the client to approve before moving ahead with any decisions, so the client was very much involved in the process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You mention that the stone was changed to paint in some parts of the bathroom, how did this not reduce quality?

A

The stone was still present in wet areas, and therefore, paint to the rest of the bathroom still met the requirements.

Further to this, cost was the client’s main objective in this scenario and therefore it achieved value for the client to make the change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The negotiated sum was below your PTE, why was this?

A

In preparing my PTE, I adopted a careful and realistic approach, allowing for remaining design development.

The tenderers were able to price more competitively given the quality and completeness of the information provided, and the competitive tender environment further contributed to returns below my PTE allowances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You say you did a cost plan 1, and then refer to an OCE?

A

Referring to the OCE was a mistake.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why did you advise using a traditional procurement route?

A

I advised using a traditional procurement route because 2 major requirements of the client were

  1. they wanted to maintain control of the design . This was going to be their family home so they wanted to have control over this, which in comparison, D&B limits.

I also knew it was highly likely there would be variations for the client altering the specification of things like fittings, which would have been likely to be more costly via a D&B route, as there would not be a detailed CSA.

The second reason was they required cost certainty, using traditional methods allowed us to receive a fixed price before entering into contract, whereas if the design was still being developed with the contractor on board, there would have been less cost certainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some risks of a 2-stage tender?

A

No certainty of the final cost.

Contractors may also essentially hide preliminary items with their elemental costs, counteracting some of the positives of defining the preliminaries in the first stage.

For this reason I use a demarkation schedule to confirm what needs to be included for within the preliminaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How could you mitigate against issues surrounding preliminary items being incorporated into the measured works?

A

A demarcation schedule was used to specify what needed to be included within the preliminaries.

With this, there still runs the risk that the contractor will inflate their measured works items, however, we undertook an open book tender to ensure that all correspondence with sub-contractors as well as quotations, were provided.

In addition to this, I market-tested packages with additional subcontractors not on the contractor tender list to provide alternative cost data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When evaluating the best procurement route for a client, what else did you consider besides time, cost, quality, time & risk?

A

I also considered other factors such as market conditions,
Size & complexity of the project,
and how progressed the design was

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were your client’s main objectives?

A

Quality & control of the design as this was their family home and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you explain to me what you advise your clients on performance bonds?

A

I always explain to the client what a performance bond is and its benefits and negatives for their consideration.

If I feel the contractor is higher risk I would advise more strongly to use this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is non-negligence insurance?

A

Non-negligence insurance protects property owners from claims arising from damage to neighbouring properties that is not due to the contractor’s negligence. It covers risks like subsidence, collapse, and vibration, even if no one is at fault.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What insurances did you advise the client on?

A

I advised that option C was required due to the property being existing.

I also advised on professional indemnity, non-negligence, public liability and employers’ liability insurance.

(other - terrorism)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did your preliminaries compare with the tender?

A

My preliminaries were approximately 13.5% of the estimate, vs the contractor at 15%.

Whilst we were similar on the weekly rate at 11k vs 10.5k, the contractor had a programme which was shorter than ours, which pushed their overall cost down.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How does A Delta system work?

A

The vacuum-formed dimpled pattern creates an air gap between the membrane and the foundation, allowing water to drain.

Typically accompanied by channels in the lab to allow for drainage, which a sump pump will remove.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Cost per m2?

A

£890/m2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How can you minimise design risk in D&B contracts?

A

Novating design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How do you manage a 2 stage tender process?

A

Two-Stage Tender: Stage 1 selects a contractor based on prelims, OH&P, capability and agrees a PCSA.

Stage 2 develops the design with the contractor, obtains subcontract prices, and negotiates an agreed contract sum before entering the main contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How can you avoid inflated costs in stage 2 of 2 stage tendering?

A

Obtain multiple subcontract quotes. Benchmark costs Control scope changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

You state ‘The current Main Contractor marketplace is very busy, and this route is less attractive due to the level of competition and risk.’, why is this?

A

Routes that involve high competition, fixed pricing, and greater risk transfer are less attractive because contractors must invest significant time and resources tendering with low chances of success

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How do you show value in budget?

A

Value in budget is shown by achieving the required quality and performance within the agreed cost limit, supported by market testing, cost control and risk management.

25
Value vs Cost?
"Cost is the amount of money spent to deliver an item or project. Value is the benefit, function or performance achieved for that cost."
26
How is microcement installed?
Applied in thin layers over a prepped surface, starting with a primer and reinforcement mesh, followed by base and finish coats that are sanded smooth and then sealed to create a durable, waterproof finish.
27
How is fibrous plaster installed?
Fibrous plaster is pre-cast off site and fixed in place using plaster adhesive and mechanical fixings, with joints filled and finished to create a seamless decorative surface.
28
why is it good to maintain a VE schedule from the earliest stages?
Identify cost-saving opportunities early, when design changes are easiest and cheapest to implement, ensuring the project stays within budget while maintaining required quality and performance.
29
What planting did you omit in VE?
Non-essential planting, including a reduction in shrubs, rhodedendrum trees and decorative planting beds
30
Did you fully omit the blinds?
We omitted the motorised blinds to all floors. Curtains were installed as an FF&E element
31
Why did you choose a JCT traditional contract without quants for this project?
JCT SBC with quantities, with approximate quantitie, but the project was generally not complex enough to require bills of quantities.
32
what are the main differences between traditional procurement and D&B?
Who holds the risk & programme
33
What did you include in the contract documentation?
JCT Contract, CSA, Design Info, Collateral Warranty Schedule, CDM, Prelims, ER's/CP's/CDP
34
Your case study says you managed the tender process. Can you talk through that process and the steps you took?
PQQ, PQQ report, prepare tender pack, go out to tender, manage tender queries/ammendments, tender returns, analysis, interviews, tender report
35
At what design stage did you go out to tender on?
RIBA Stage 4/5
36
Management routes were discounted - what are the main management routes and why did you discount them ?
Construction Management & Management Contracting; the client wanted early cost certainty and didn't have the experience or resource to be overly involved. Programme was not critical.
37
D&B single stage discounted - What could limit the risk of havng bad quality when using a D&B route?
Clear and detailed Employer’s Requirements and novating the employers design team over
38
How does your role as a cost manager/quantity surveyor differ, when using a D&B route instead of a traditional route?
- EA in D&B and CA in standard contract. - The employer's agent represents the employer and manages the overall project, while the contract. - Administrator focuses on overseeing the contract between the employer and the contractor.
39
What is one of the key things you need to have in place for the second stage of a two stage tender process?
Clearly defined and developed scope of works & design information
40
OHP & Prelims provided as part of stage 1, what are these? Can you give some examples of prelims items?
Overhead & Profit - Overhead the cost to run the business & profit the money they make. Prelims - the items/costs to run the site, outside of the actual construction works, e.g. management, site set up, PPE
41
In what format would the contractor submit their price at the second stage?
CSA
42
You say this Option 2 couldn’t fufill the clients needs for cost certainty? Why not?
The contract sum is not fixed at the first stage and remains subject to ongoing design development, package procurement and negotiation during the second stage.
43
You included a pre qualification process? What is this and why is it important? What follows after the PQQ is done?
Used to assess/shortlist contractors before inviting them to tender. Ensures we are only tendering to appropriate contractors. Following the PQQ is a PQQ report and then going out to tender.
44
What is one of the key benefits of traditional procurement when reviewing tenders?
Complete design information should mean they can be priced like for like and easy to compare
45
Disadvantage - MC market is very busy, and this route is less attractive due to level of competition and risk - less attractive to who?
The contractors - Less attractive to main contractors due to the high level of competition and risk in a very busy market
46
How did this route ensure that a high quality design was maintained?
Design is complete before tender, fixing materials, specifications and performance standards. Client maintains control of the design with their team
47
You prepared Formal cost plan 1? How did you do this?
Reviewed the brief and design information, took the measures in line with NRM 1, built up rates using benchmarking, historic project rates & market testing, identified risks & allowed for contingency, QA, review & issue
48
What industry guidance are you aware of in relation to the cost planning exercise completed?
NRM 1 & Code of Measuring Practice
49
You then mentioned Cost plan 1 then mentioned OCE, which was 500k more than your previous estimate? Do you mean PTE?
I meant OCE then Cost Plan 1
50
How did you go about putting together the cost plan that equated to 5.6m? What information was this based on?
RIBA Stage 3 information. Reviewed the brief and design information, took the measures in line with NRM 1, built up rates using benchmarking, historic project rates & market testing, identified risks & allowed for contingency, QA, review & issue
51
How did you test the estimate of 5.6m to ensure that it was accurate?
I carried out benchmark comparisons against similar projects to check overall cost per m2
52
Why did you present a budget increase as an option?
It would allow the project to proceed without any impact on programme
53
Was budget increase viable? How did you know the client was able to increase the budget?
Yes, a limited budget increase was viable. The Client confirmed they had some flexibility within their funding arrangement.
54
What are risk allowances? Were risk allowances factored into the cost plan for budget overruns?
Allowances included in the cost plan for unforeseen events. Appropriate risk allowances were made, but the increase was primarily due to scope and specification changes.
55
390k VE list. How did you cost the VE options?
Estimate a cost for the VE item and do a cost comparison to what is in the cost plan to find the cost saving.
56
How does value engineering differ to value management?
Value management involves determining what value means to the client and their objectives, value engineering is a cost focused exercise to reduce cost without compromising quality & functionality.
57
110k remaining over budget. Could you have reviewed further VE options, to avoid having to omit scope?
Yes - but these items got rejected. For examples, we also reviewed changing the ironmongery & faceplates
58
Did the scope omissions have any effect on the overall quality that the client wanted to achieve?
Yes - but it was limited and controlled. The items omitted were non-critical to the client.
59
In hindsight, key issue 2 could have been minimised'…you said before time wasn’t an issue to the client, so just be cafeful of that last paragraph
A number of decisions needed to be made within a short window to maintain design progression and avoid disruption to the design team’s workflow and can also lead to additional fees.Time pressure related to decision timing, not programme constraint.