Construction Tech MO Flashcards

(83 cards)

1
Q

Types of foundations?

A

Piled, Pad and Strip

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are Piles?

A

Long columns driven or bored into the ground to transfer loads to stronger, deeper ground.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you price piles?

A

Number of piles (count)

Length per pile (linear metres)

Diameter (mm or m)

Plus ancillary items, e.g.:

Cutting down pile heads

Reinforcement (mass per pile or per m)

Pile caps / beams

Testing (static load, integrity, dynamic)

Temporary casing or bentonite support (for bored piles)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When do you use piles?

A

Weak/poor soil/bad ground conditions, heavy loads & basements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are underpins?

A

Underpins are blocks or sections of a new foundation built beneath or beside an existing one to strengthen or stabilize it, transferring the load to stronger ground below.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Types of piles?

A

Driven, bored, sheet, mini

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Piles - Advantages & Disadvantages?

A

Pro’s - heavy loads, can be used in poor soil.
Con’s - Expensive, specialist, sound/movement for neighbours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are bored piles?

A

Drilled using an auger/rotary rig, used for basements, deep foundations. They cause low vibration & noise. But are slower, more expensive and spoil management is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are driven piles?

A

Hammered to vibrated into the ground. Good for new builds (open access). Fast installation & quality control. But cause a lot of noise & vibration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are sheet piles?

A

Sheet piles are steel sections driven into the ground to form a wall.

Pros: Quick to install/remove, minimal excavation, reusable.

Cons: Noisy, vibrations, limited in hard ground, may need support, can corrode.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are mini piles?

A

Drilled/grouted with a rig, used for basements and where you are also underpinning and have restricted access. Minimal vibration but more piles required and is slow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are CFA piles?

A

CFA Continuous Flight Auger piles

Bored, cast-in-place concrete piles formed using a continuous auger to drill into the ground and then pumping concrete through the auger stem as it is withdrawn — creating the pile without ever leaving the bore open.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you price underpins?

A

Underpins are priced by volume or per pin, based on type, depth, and access. Rates include hand excavation, concrete, reinforcement, and temporary works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are pad foundations?

A

Pad foundations are individual blocks of concrete that support single point loads e.g. columns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are strip foundations?

A

Strip foundations are continuous strips of concrete that run under load bearing walls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When do you use pad foundations?

A

Ground had good bearing capacity, with steel and concrete frames. Pros cheap, quick, easy to inspect. Cons not suitable for weak ground conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When do you use strip foundations?

A

Masonry/framed buildings, moderate bearing strength. Pros economical & low risk, cons not suitable for weak ground conditions and only used for low rise buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is raft foundations & when do you use them?

A

A raft foundation (also called a mat foundation) is a large, thick reinforced concrete slab that spreads the load of a building over a wide area, often the entire footprint of the structure. Weak or variable ground, large building footprint, Light to medium loads, low rise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Steel vs Concrete frame?

A

Steel Frame: steel column & beams support floors & roof. Loads carried through the frame, walls are non loadbearing. Pros fast, high strength to weight ratio, recyclable. Cons fireproofing, potential corrosion, expensive.

Concrete Frame: Frame made from concrete columns, beams & slab. Loads transferred through the RC frame to the foundations. Pros - fire & accoustic performance, flexible shapes, durable, low maintenance. Cons slow & heavy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Life Cycle Costing vs Whole Life Cycle Costing?

A

Life Cycle Costing: includes capital, maintenance, operational, replacement and disposal costs for a building.

Whole Life Cycle Costs: The total cost of ownership over the life of an asset, including acquisition, operation, maintenance, and disposal costs, plus the costs (or benefits) of externalities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the approved documents?

A

Approved Documents are official government guidance that explain how to meet the functional requirements of the Building Regulations in England.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Examples of approved documents?

A

A - Structure - stability, loading, etc.
B - Fire Safety - Means of escape, fire spread, access for fire services
C - Site Preparation & Resistances to Contaminants/moisture

L - Conservation of fuel & power - energy efficiency, insulation, U-values
M - Access to & use of buildings - disabled access, step free entry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Are approved documents mandatory?

A

They are not mandatory — but following them provides a “deemed-to-satisfy” route to compliance.
If you follow what’s in the Approved Documents, Building Control will normally accept that your design meets the Regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How do you construct a basement?

A

Excavation, piling (CFA piles), underpinning (neighbouring property), basement slab, external walls, waterproofing (waterproof concrete & cavity drain).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
How do you price basement construction?
Enabling & temporary works (hoarding, scaffolding, propping, facade retention) Piling or underpinning (retaining structure) Bulk excavation & disposal Waterproofing system (Type A, B or C) Reinforced concrete works (base slab, walls, columns, capping beams) Drainage & sump pumps Fit-out (M&E, finishes, stairs, lighting) Element Unit Notes Excavation to reduced level m³ Include temporary supports, over-dig, working space Piles or underpins m / m³ By diameter, depth, or number of pins Concrete to base slab / walls m³ Include reinforcement and formwork Waterproof membrane / cavity drain m² By system type Drainage and sumps m / no. With pumps and chambers Backfill m³ Type and compaction Waterproof screed or insulation m² Floor buildup Internal fit-out item / m² Finishes, M&E, joinery, access
26
Cost per m2 of a recent basement construction you priced?
£1,900/m2
27
How do you price temporary works?
Scaffolding Facade retention frame - columns, walers, props, bolts & fittings Propping Shoring Design, Installation & Removal
28
What façade type was Rutland gate?
Render finish over a brick & block wall
29
Types of façade?
Masonry (brick, stone, blockwork) Curtain Wall (non load bearing external wall fixed to the building structure) Precast Concrete Façade (Large concrete panels cast off-site and lifted into place as part of a structural or non-structural envelope.) Timber Façade / Timber Cladding Glazing
30
How do you retain a façade?
To retain a building's facade, it is either temporarily supported with external or internal steelwork while the interior is rebuilt, or the facade is carefully dismantled, stored, and then rebuilt.
31
How did you price façade retention?
Steel retention frame - external steel retention frame with walers and needles, raking props, temporary foundations for the frame Protection of retained structure Demolition New structure built, movement joints included
32
What temporary works did you do?
The facade was temporarily propped by a steel frame.
33
Examples of the benefits of the two options on Rutland Gate (Façade retention or New Build)?
New Build: Shorter programme, lower cost, easier construction Façade Retention: Already had planning approval
34
Which option was more cost effective on Rutland Gate (Façade retention or New Build)?
New Build
35
How do you price services?
per m2 or speak to an M&E surveyor
36
What is delta membrane?
Cavity Drain Waterproofing system; essentially collects the water and directs it to a sump pump where it is then removed to an external drainage point
37
What did you advise on Rutland gate?
That the more cost and programme efficient option was new build.
38
How did you under take the cost analysis of Façade retention vs New Build?
I compared façade retention and new build by preparing elemental cost plans I analysed key differences in demolition, temporary works, and preliminaries. Compared cost & programme factors to help the client make a decision.
39
What prelims cost did you consider when comparing the Rutland Gate options?
Time related prelims mainly, as the programme was increasing by approx. 25 weeks
40
What was the issue in terms of the condenser units on Victoria Road?
Where to put them, between the roof and the basement
41
What did you advise on Victoria Road in terms of the condenser units?
That the roof was more cost effective
42
How did you cost the two options on Victoria Road?
Roof Option: Removal of existing roof, modification of existing roof structure to allow new flat roof area, plinth, additional works (pipework, fixing etc.) Basement: Reinforced basement underpins Reinforced concrete capping beam; 350mm x 600mm 150mm thick well compacted hardcore Blinding; 50mm thick 100mm FOAMGLAS T4+ slab insulation Reinforced screed; 70mm thick Kingspan Thermalon TF70 insulation; 70mm Isocrete K screed; 70mm Excavate for new basement Compact bottom and sides of excavation Reinforced concrete liner wall Cetco Voltex waterproof membrane Cavity drainage membrane to walls Cavity drainage membrane to floor Secondary System - Waterproof Concrete Concrete Slab; 275mm, Formwork, Reinforcement and Insulation Louvred screen and door to plant room
43
What is PI?
Professional indemnity (PI) insurance is liability insurance that covers professionals and companies against claims of negligence, errors, or omissions in their advice or services.
44
Name a project where you priced piling?
Victorria Road
45
What piling would you use for a retaining wall?
Steel sheet piling or CFA piling
46
You estimated costs for beams on Rutland Gate? What type of beams and how?
On Rutland Gate, I estimated costs for structural steel beams forming part of the frame. “I estimated the beams using tonnage-based rates from benchmark data and subcontractor input. I included fabrication, erection, connection detailing, and temporary works.
47
What was the difference in total cost between the façade retention option and new build option?
£1.5mil (£140k more strip out, 25 weeks more programme 1mil)
48
What is run off cover?
Run-off cover is PI insurance that protects a firm after it stops trading, covering any claims made later for work done before it closed.
49
What is CHP?
CHP – Combined Heat and Power Generates electricity and heat at the same time from one fuel source (usually gas). The electricity powers the building, and the waste heat is reused for heating or hot water. Improves efficiency and reduces energy waste, but relies on fossil fuels unless adapted for renewables.
50
What is ASHP?
Extracts heat from the outside air (even when cold) and uses it to heat the building. Works like a reverse fridge. Cheaper and easier to install than GSHP, but less efficient in very cold weather.
51
What is GSHP?
GSHP – Ground Source Heat Pump Uses heat from the ground to warm the building. Pipes buried in the ground absorb natural heat; a pump transfers it into the heating system. Efficient and sustainable — low running costs but high installation cost.
52
GSHP or ASHP?
GSHPs are more efficient year-round due to consistent ground temperatures, but have high upfront costs for installation. ASHPs are cheaper and easier to install, but are less efficient in cold weather, leading to higher running costs during winter.
53
Name some M&E systems?
Cooling / Air Conditioning; FCU, VRF/VRV Fire Protection: Sprinklers, dry risers, wet risers, suppression systems Power distribution: The generation, transmission, and distribution of electricity throughout a building. Lighting: Both interior and exterior lighting systems. Security and safety: Fire detection, alarm systems, and access control.
54
What are condenser units?
A condenser unit is the outdoor component of an air conditioning or heat pump system that releases heat to the outside air to cool the indoor space.
55
How do you price frames?
Calculating the total tonnage of steel, applying rates for material, fabrication, and erection, and adjusting for complexity
56
What is BREEAM?
Building Research Establishment Environmental Assessment Method
57
BREEAM Scoring?
Unclassified: Less than 30% score. Pass: 30% or above. Good: 45% or above. Very Good: 55% or above. Excellent: 70% or above. Outstanding: 85% or above.
58
What is BSR?
The Building Safety Regulator (BSR), part of the HSE, was created by the Building Safety Act 2022 to improve building safety. It oversees higher-risk buildings, raises safety standards, and ensures competence across the design, construction, and building control sectors.
59
What is HRB?
HRB stands for Higher-Risk Building in the context of the Building Safety Act in the UK. It refers to a building that is at least 18 meters high or has at least seven storeys and contains at least two residential units.
60
What is the BSA?
The Building Safety Act 2022 improves building safety by introducing stricter rules for higher-risk buildings (over 18 m or 7+ storeys). It establishes the Building Safety Regulator (BSR) and defines clear duty holder responsibilities for design, construction, and building management.
61
What are the gateways in BSR/BSA?
**Gateway 1 – Planning Stage** Fire statement required with planning application. Local authority must consult the HSE. **Gateway 2 – Pre-Construction** “Stop/go” point before work starts. Building Safety Regulator (BSR) must approve detailed design for Building Regs compliance. **Gateway 3 – Completion** Final “stop/go” before occupation. BSR confirms as-built works meet approved plans and Building Regs. Completion certificate issued → only then can building be occupied.
62
When preparing early estimates, how do you decide what foundation types to cost for?
Depending on ground conditions, loads, building height.
63
What are some different types of Waterproofing?
Type A: Bentonite Slurry / Tanking Type B: Waterproof Concrete Type C: Cavity Drain Membrane
64
What is Bentonite Slurry / Tanking?
A barrier system where bentonite clay or cementitious slurry is applied to the structure; it swells on contact with water to form a waterproof seal that stops water entering the basement.
65
What is waterproof concrete?
The basement is built using watertight reinforced concrete, with cracks kept very small and additives mixed in to help resist water, so the structure itself stops water getting in.
66
What is Cavity drain membrane?
A studded plastic membrane is fixed to the walls and floor, allowing water to enter the cavity and be controlled and drained to a sump and pump system, rather than trying to stop it. The sump pump then pumps it up and out into a drainage system
67
Different classifications of basements?
Basements are classified by the level of water resistance required: Grade 1 – Basic utility Some water ingress acceptable (e.g. car parks, plant rooms). Grade 2 – Better utility No water penetration, but dampness tolerated (e.g. storage areas, workshops). Grade 3 – Habitable Completely dry environment required (e.g. bedrooms, living spaces, offices).
68
What is the structure of Victoria Road?
A piled and underpinned basement, supporting a steel frame superstructure, with solid masonry external walls finished in rendered or stuccoed brickwork.
69
When is a steel frame more suitable?
When speed of construction is important, Reduced structural weight is needed (basements, or poor ground)
70
What is formwork and what formworks are there for concrete buildings?
**The temporary mould used to shape and support concrete until it gains sufficient strength** **Slipform** – continuous pour system used for cores and high-rise structures **Jumpform** / climbing formwork – used for vertical elements like lift cores **Tunnel** formwork – casts walls and slabs in one operation (housing/high-rise)
71
What year was Rutland Gate built?
1985-1987
72
What is Curtain walling?
Curtain walling is a non-loadbearing external façade system, typically made of glass, aluminium or steel, that is hung from the structural frame of a building
73
When is curtain walling used?
Curtain walling is used on buildings where a lightweight, glazed façade is required without carrying structural loads.
74
What are some key risks in basement builds?
"Ground Obstructions Contamination Archaeological"
75
How do you waterproof concrete?
Add an additive into it
76
What is a bitumen membrane?
A bitumen membrane is a waterproofing material made from bitumen (a petroleum-based product), used to prevent water ingress in areas such as roofs, basements and foundations. It is typically applied as rolls or liquid coatings
77
Cost factors that effect steel costs?
Transport costs, tarrifs & ukraine war
78
Why use bored over driven piles?
Vibration and noise must be minimised, such as near existing buildings or party walls Ground conditions are variable, allowing pile depth and diameter to be adjusted during drilling
79
What is a construction risk?
A construction risk is any unforeseen event that may occur during a construction project
80
What is the structure of 50 Victoria road?
Piled and underpinned basement, steel frame superstructure, and traditional solid masonry external walls.
81
Why use steel for high-rise buildings?
For its strength, speed of construction, reduced weight and flexibility
82
Risks of cavity drain membrane?
Maintenance requirements and man hole connections etc.
83
Tell me about waterproofing systems?
Waterproofing system requires two forms, which in this case where the secant piles to to its density and the delta membrane, backed up by a sump pump.