How did you identify the Clients key priorities?
Tell me the contractual timescales you complied with?
You mention raised access flooring, can you tell me what this is?
You mention Risk Registers, what are these for and how are the risks measured?
Why did your Client want to proceed under the D&B Contract and what advise did you give them?
My Client is a residential managing agent, with no experience in Building Contracts and the like. Therefore, I agreed the best procurement route was the Design & Build Contract. This allowed my Client to push all design responsibilities and risk onto the Contractor.
What is Building Control?
And are there any legislations around it?
What formed the Contract Documents?
You mention lettable cost per m2. What’s included or excluded within this rate?
What is the difference between:
- CAT A+
- CAT A
- CAT B
CAT A+ - This included tea points to the office space.
CAT A - This was stripped back to shell, to allow tenants to provide their own fit-out and branding.
CAT B - On the first floor, was a completed, ready to use space. Including, internal partitions, decorations, flooring, ceiling finishes etc.
What are the Building Regulations?
Can you name any?
Part A - Structure
Park B - Fire safety
Part P - Electrical
Where have you demonstrated the data management competency within your case study?
How did you identify the stakeholders?
Created a stakeholder register with contact details
How did you ensure you maintained a good client relationship?
My Achievements
You state the project was delivered within budget. How did you report this to the Client?
This was reported to the Client within my monthly Cost Report, demonstrated in the executive summary element.
Did you advise anyone else of their duties under the contract?
What insurances should be in place on a Construction project?
What is Contractors all risk insurance?
What is a CSA and when in the project timeline is likely to be used?
How did utilising a PCSA ensure Cost Certainty?
Following the tender process, the PCSA allowed me to fix a Contract Sum with the preferred contractor, enter into the PCSA with the contractor and complete the design works as part of the list of deliverables, without engaging the Client into a full contract at this early stage.
CASE STUDY: What was included on the letter of intent? Does it stand up contractually
CASE STUDY: Was a PTE undertaken prior to the contractor submitting their tenders over budget?
No, a PTE was not carried out. We were not appointed to carry out a PTE.
CASE STUDY: MEP was quite a large cost, what were the key drivers in it? What would you typically expect MEP to be in % terms of a project budget?
CASE STUDY: Would you usually expect provisional sums in a design and build project?
its not uncommon to have provisional sums within a D&B. These are allowances where the contractor may need further information to be able to provide a fix cost.
CASE STUDY: You mention internal cost data and benchmarking, what would you consider whilst using this information?
I would consider that the benchmarking costs are I am using are relevant and in proportion to the project I am costing.
CASE STUDY: Were there any damages in place if the completion date were missed? How were these calculated?
Yes, a weekly sum was included of around circa £5k per week.