What are the minimum expectations of the Contract Practice competency?
What takes precedence under a JCT D&B - ER’s or CP’s?
ER’s take precedence
Where there are discrepancies under the ER’s. and CP’s clarify, this overwrites the discrepancy. E.g. ER’s state gold taps but ER drawings show brass and the CP’s reflect brass, then the CP’s set the requirement
What types of change are there? When can they occur?
May occur pre-contract, near end of concept design or during tender stages with amendments to documetns
Post-contract
What is a variation?
In D&B referred to as variations
How do NEC contracts deal with change?
What are the valuation rules under contracts you have worked on?
What is the process for change management that should be followed?
Set out on contracts in Section 3.
On NGH (D&B):
’- Oral instruction
- Requires contractor to confirm terms in writing in 7 days
- Client to confirm within 7 days (or takes effect from the expiration of the 7 days
- Intsruction applies
If no confirmation received from client, can be confirmed retrospectively before the final due date
Name some changes that may occur
What would you review when a change has been identified?
What do you know about FIDIC contracts?
International Federation for Consulting Engineers
- Employer instructs variations
- Claim is a variation
- Internationally used
- Engineer acts as CA
- Red book - Employer designed
- Yellow book - Contractor designed
What are the valuation rules for a Standard Building Contract?
What is a fair and reasonable rate?
Not case law, open to interpretation
Should be considered in reflection that there is no market competition
What is change under a SBC?
Variation!
Alteration of design, quality or quantity of works
Imposition by employer of any obligations or restrictions
What is change under a D&B?
Change!
Changes to ER’s
Imposition by employer of any obligations / restrictions to working e.g. access / limited working hours
What are the valuation rules of a D&B contract?
How are changes valued under NEC?
Compensation events
- Assessed based on defined costs of works already done and the forecast costs + contractor fee
- Under B there are specific CE’s including inaccurate quantities, items that are more than 0.5% of prices at contract sum that constitute change
How are changes valued under FIDIC?
Valued by Engineer
- Contractor prepares proposals
- Rates are adjusted if the quantity varies by more than 10% from the BoQ or changes in the unit cost is more than 1%
- VE opportunities follow the same rules- contractor shares any savings made
What are star rates?
Used where contract rates are not applicable