Why may fluctuation clauses be important at the moment?
What if a contract does not include for fluctuations? Is there a way of being able to adjust the contract sum?
Only if there is a variation or an entitlement to an EOT & L&E
Can a contract be terminated if inflation makes it commercially unviable?
Unlikely to be an option
If terminating party gets it wrong, they run the risk of a breach of conflict by which damages can be claimed such as additional costs of getting work completed by others
Why is the base date important for fluctuations?
Fluctuation provisions apply from the base date
Base date is usually the date of the tender or priced offer meaning risk of inflation between tender and construction is with the contractor
If the base date is the date of execution or commencement of works, then the risk of inflation over the period sits with the Employer
What are fluctuations?
Term used to describe the method of dealing within inflation (or deflation) in construction
Why would you use fluctuation clauses?
Where fixed price, the Contractor usually assumes all the risk on the cost of items which becomes problematic on long projects or during times of high inflation
Can cause tender prices to be higher
Allows a fairer way of calculating the actual cost
Under a fluctuating contract, employer is not bound by the contractor estimate of change, they only pay what is actually incurred
Where are fluctuating clauses found in contracts?
How may fluctuations be captured in different types of contract?How may fluctuations be captured in different types of contract?
-Lump sum: rates would be adjusted as appropriate. Formula adjustment using series of indices
-Remeasurement: rates adjusted as appropriate
-Framework agreements: arrangement with Contractor over period of time. Contracts are “call-off” or tendered over time so each contract sum will be current at the point of signing, so will reflect fluctuations to that point. May also be provisions within the contracts
-CM / MC: agreed at each point of contract. Usually a mechanism to allow for adjustment of manager fee and central costs e.g. site welfare / security
Where are fluctuations likely to cause disputes?
When construction period is delayed or works change
Can create concurrent delays making it difficult to manage risk
Area of evolving law
How are fluctuations managed with exchange rates?
What is an indices?
A measure made up from a variety of sourced. Regional variations where labour material and plant costs may vary
What should be considered when choosing indices to assess fluctuations?
Need to be produced by third party & published for duration of project
What is a QS’s role in assessing fluctuations?
According to NRM, what are the 2 types of contracts relating to fluctuations?
What options are available to deal with fluctuations in a JCT?
Option A - fluctuations in contributions, levies and taxes
Option B - fluctuations in labour, materials and taxes
Option C - some items are fixed but others are variable. Price adjusted using BCIS data
Default is option A
Can all options apply to all types of JCT?
Intermediate - A only
Minor works - A only
How do NEC Lump sum contracts deal with fluctuations?