1. Which of the following measures the amount of data that might be potentially lost as a result of a system failure? a. recovery time objective (RTO) b. recovery point objective (RPO) c. disaster recovery plan (DRP) d. business continuity plan (BCP)
b. recovery point objective (RPO) (Correct. The RPO measures the time between the last
data backup and the occurrence of a problem.)
2. Prenumbering of all source documents is a mitigating control to preserve processing integrity at what stage of the process? a. input b. processing c. output.
a. input [Correct. Prenumbering improves control by making it possible to verify that no
documents are missing.]
d. a stability check [Correct.]
a. True [Correct. Reasonable test is an edit check of the logical correctness of relationships
among data items.]
a. Incremental daily backups are faster to perform than differential daily backups, but
restoration is slower and more complex. (Correct.)
b. processing controls. [Correct. Processing controls ensure that data is processed
correctly. ]
b. the sum of the purchase order number field in a set of purchase orders (Correct. The
sum of purchase order numbers has no intrinsic meaning.)
d. All of the above are true. (Correct.)
b. A cold site. [Correct. A disaster recovery option that relies on access to an alternative
facility that is prewired for necessary telephone and Internet access.]
c. check sums. [Correct. A data transmission control that uses a hash of a file to verify
accuracy. ]