What are the two levels on which project evaluation takes place?
- Summary evaluation: after project completion
What are the different ways of collecting data for formative evaluation?
Name the three main aspects of formative evaluation
What must a communication plan include?
• Schedule for project reviews • Milestone meetings • Important points of contact - Customer - Contractor - Stakeholders
What are the main purposes of status review meetings?
* Identify deviations and quickly correct them
What are the three different forms of status review meetings?
Why is informal communication important?
It provides the project manager with insight into team dynamics and other project aspects which are not formally reported on
What is the project implementation stage?
Product or system is handed over. This includes user acceptance, training and testing
What are the three ways of implementing a new system?
What are the three kinds of project termination?
What is the main responsibility of the project manager during project termination and closeout?
Scheduling, planning and monitoring of closeout activities
What are the main closeout activities?
What are the FINAL closeout activities?
Name the closeout activities related to customer and payment
What does the summary evaluation review?
The performance of the project team and the end-item system or product
What are the two forms of summary evaluation?
- Post-installation system review
What are some of the main aspects covered in the post-completion project review?
What is the focus of the Post-Installation review?
The end-item (or product), not the project or project management process
What is the output of the Post-Installation review used for?
Final changes and enhancements to product/system (but this should be new project)
What does the organisation use a Post-Completion Project review for?
The summary review and assessment of the project is used is applied to enhance the performance of the organisation in future projects