What is a critical path?
The longest path from start to finish for the project. Activities with zero float are considered critical path tasks.
What is duration compressing?
The use of techniques such as fast-tracking or crashing to shorten the planned duration of a project or to resolve schedule slippage
What is a mandatory dependecy?
A type of dependency where the relationship between two tasks is created by the type of work the project requires.