Chapter 5 Close Projects Flashcards

Discuss how to conduct final deliverables & verify all the tasks are done. & Explain the project and closure process. (10 cards)

1
Q

What is the process for ensuring that a building’s performance is in harmony with the intent of its design and the operational needs of its owner?

Certificate of occupancy

Warranty

Commissioning

Retainage

A

Commissioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible for deliverables, once formal acceptance takes place?

The project manager

The owner

The construction project manager

The quality control person

A

The owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Finished deliverables for a construction project are found to be deficient but are repaired & validated. If the owner is still not satisfied, what happens next?

Correction and validation continue to occur until the owner is satisfied or project is cancelled.

The project is closed regardless of whether the owner is satisfied.

Correction and validation can occur once more, but if validation is successful, the project is closed even if the owner is not satisfied.

None of the above

A

Correction and validation continue to occur until the owner is satisfied or the project is cancelled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can be used to ensure liens are cleared at project completion?

Retainage

Warranty

Maintenance agreements

Commissioning

A

Retainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What validates the deliverables that need correcting?

Quality assurance

Quality control

Team member originally responsible for the work

Project management software

A

Quality control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is an informal walk-through of a construction site performed prior to the formal walk-through?

To see that all work appears complete

To verify that all contactor tools have been removed

To ensure the site is clean

All these statements are correct

A

All statements are correct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In a construction project punch-list review, which is true?
Project managers complete the punch list on their own.

Incomplete work on the site is acceptable if they are areas prepared for owner -furnished items.

Project managers should point out every flow, no matter how minor and get them fixed.

The site will still have substantial debris and construction tools that need to be avoided.

A

Incomplete work on the site is acceptable if they are areas prepared for owner-furnished items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is done both before and after a relocation to measure the increase in satisfaction with the new space?

Root cause analysis

Occupancy surveys

Balanced scorecard innovation and learning perspective

Action and change order analysis

A

Occupancy surveys

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which is true of outcome evaluations?

Outcome evaluation reports are developed for the project manager and executives only.

business value analysis is best conducted immediately upon project completion.

Action and change order analysis tries to minimize change order situations in future projects.

Root cause analysis is performed only for project failures.

A

business value analysis is best conducted immediately upon project completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly