What is needed for a contract to be formed?
Capacity
Intent
Offer
Consideration
Acceptance
Legality
Can you give an overview of the structure of the NEC?
Core Clause - payment, CE’s, insurances, time
Main Options;
- Option A Priced with Activity Schedule
- Option B Priced with BoQ
- Option C Target With Activity Schedule
- Option D Target with BoQ
- Option E - Cost Reimbursable
- Option F - Management Contract
W Clauses (Dispute Clauses - W1, 2 & 3)
X Clauses (performance bond, PCG, sectional completion, retention, LAD’s)
Y Clauses (National Legislation)
Z Clauses (bespoke amendments)
Can you name some of the contracts in the JCT Suite of contracts?
What types of pricing options are there?
Can you identify some differences between NEC and JCT?
What are the payment timelines under PPC2000?
What are the different types of subcontractor?
Domestic - selected through competitive tender.
Named - client provides a list for the main contractor to use for competitive tender.
Nominated - Proposed by the client and must be used.
What are LAD’s?
Damages inserted into the contract that the client can claim in the event of non-completion by the contractor.
How does the structure of JCT contracts differ to NEC?
Under JCT everything forms part of the standard contract whereas under NEC there are core and optional clauses so there is the ability to adapt the standard contract without making amendments.
How do CE’s under NEC differ to variations under JCT?
What is Novation?
Transfer of rights and obligations under an existing contract, for example under a D&B contract the design team is novated from the client to the contractor.
What is a Collateral Warranty?
A document which creates a contractual link between two parties under an existing contract where one does not already exist, for example between client and a subcontractor.
Allows the client to claim from subcontractors in event of a breach.
What is a Letter of Intent?
A non-binding letter which outlines an agreement in principle prior to the contract being executed.
What are the different types of Letter of Intent?
Comfort Letter - provides contractor comfort
Consent to Spend - allows contractor ability to place orders
Recognition of Contract - all terms have been agreed however awaiting final signing of contract
How would you select the most appropriate form of contract for a project?
Can you outline the payment process and timescales under a JCT D&B?
21 day process in total starting with contractor submitting their application.
Due date is 7 days after this.
14 days from due date is final date for payment.
Payment notice should be issued no later than 5 days from the due date.
Pay less notice should be issued no later than 5 days before final date for payment.
What forms of performance security exist for a client?
What is a Performance Bond?
Contractor takes out for a sum of money and in the event of a default the client can claim this money.
There are two types; on demand and default.
What is a Parent Company Guarantee?
A PCG is in the event of a company defaulting, their Parent Company then because responsible for fulfilling their obligations under the contract.
What is the duration of a PCG?
Dependant on how the contract was signed;
Underhand - 6 years
Deed - 12 years
When does a Performance Bond end?
At the end of the defect liability period - once the certificate of making good has been issued.
Different types of insurance under a construction contract?
Construction Works Insurance
Professional Indemnity
Public Liability
Employers Liability
Who takes out the Construction Works Insurance under JCT.
Option A - New build - Contractor
Option B - New Build - Employer
Option C - Works to or extensions to existing buildings - Employer
What is the benefit of a joint names policy?
Both parties are protected - so If a contractor makes claim against employer and they are not named then the employer is not protected so they are liable for the outcome of the claim. Avoids subrogation.