What are the six basic components of an owner-vendor agreement (or owner-contractor agreement)?
This document is composed of:
What are the four types of written modifications that can be made after the execution of a contract?
Four examples of this are:
What are five of the most common variables that can affect the cost of a project when bidding occurs?
This aspect of a project bid can be affected by the:
What seven types of information are typically included in the instructions to bidders?
This document typically gives information about:
What is an addendum?
This is a written or graphic document issued by the interior designer before the execution of the contract that modifies or interprets the bidding documents by additions, deletions, clarifications, or corrections.
What are five of the responsibilities of the owner during furniture installation?
During this phase of a project, the owner is responsible for:
What are liquidated damages?
These are moneys paid by the contractor to the owner for every day the contractor is late at completing a project.
What form does a vendor or contractor use to request payment from the owner?
An Application for Payment form is used for this.
What is a unit price?
This is a set cost for providing a portion of the construction work that is based on an individual quantity, such as per unit or per square foot.
What is retainage (also called holdback in Canada)?
This is a percentage (usually 10%) of each payment to a contractor or vendor that is withheld by the owner for the purpose of protecting the owner against incomplete or defective work.
At the owner’s request, a contractor may include alternates in the bid documents. What is an alternate?
This is a construction item that could, at the owner’s discretion, be substituted for a similar item in the base bid to reduce project costs.
If all bids on a project exceed the owner’s budget, what four options are available to the owner?
If this happens, the owner can:
What is the purpose of a labor and material payment bond?
This is used to guarantee payment for labor and materials on a project if the contractor defaults or otherwise fails to make payments.
Under what conditions can a contractor propose substitutions during bidding?
Bidders must request written approval of these at least 10 days before bid opening. The request must include documentation showing that the proposal meets the requirements of the contract documents.
What is a performance bond?
This is a statement by a surety company that obligates the surety company to complete construction of the owner’s project if the contractor defaults.
What is bid security?
This is a certified check, cashier’s check, or bid bond requested by the owner to ensure that the successful bidder will fulfill the contract.
What are the four primary advantages of negotiating a contract?
Some of the advantages of this process include:
In regard to interior design, what is substantial completion?
In the construction project, this is the stage when the work, or a designated portion of it, is sufficiently complete according to the contract documents that the owner can occupy or use the site, even though a few minor items may yet need to be finished or corrected.
What are the two common ways to notify prospective contractors that a project is being bid?
The two common ways to accomplish this are to:
How is a negotiated contract different from a bid (or tendered) contract?
With the former, the owner selects a contractor to do the work, and the two discuss the cost and terms of the contract.
With the latter, several contractors view the contract documents and submit cost proposals.
In regard to interior design, what is an allowance?
This is a set amount of money that the interior designer estimates will cover the cost of a particular item (construction or furnishing) when that cost cannot be determined precisely at the time of the bid or negotiated proposal.
What two types of contracts are typically used on large commercial interior design projects?
This type of project calls for two contract types:
What is involved in generating a fee projection?
In this process, the total fee the designer will receive, after amounts for profit, overhead, and other expenses are deducted, is allocated to the schedule and to the various staff members who will be completing the project.
What are the five basic activities of project management?
This task involves: