What happens at Practical Completion?
What’s the difference between a change and an instruction? (two separate items in relevant events in the JCT contract)
Change/variation = difference to works either from additional/unforeseen works or employer changing mind.
Instruction = doesn’t necessarily change works, e.g. expenditure of provisional sums, for emergency action to be taken by contractor, for opening up of completed works for inspection.
What is the HGRCA 1996 (Construction Act) and what did it do for construction projects?
Housing Grants, Regeneration and Construction Act 1996
What is the role of a Contract Administrator?
1) Duties (such as providing necessary information to the contractor), which are carried out as agent of the employer.
2) Certain decision-making functions (such as the certification of work properly carried out) in which the contract administrator is required to act fairly between the parties and exercise independent judgement
- Issues instructions, including variations or change orders
- Settles the adjusted contract sum (final account)
- Determines any applications of extensions of time by the contractor
- Certified the date of completion
- Authorises interim payments to the contractor
- Periodic inspection of works
What does the JCT Contract Administration Guidance Note cover?
The roles and responsibilities of the Contract Administrator, specifically in relation to:
Can you outline your key responsibilities as Contract Administrator for the Australian Embassy project?
What are the implications of issuing P.C.?
What are the implications of issuing CMGD?
What are the key differences between the change control processes on NEC and JCT contracts?
What would you do if the contractor has not completed by the PC date?
Issue a certificate of non completion
What is a payless certificate?
The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation. This has to be issued >5 days prior to payment date.
What must a contractor do if a CA issues an instruction?
Comply within 7 days
Failure to comply, the employer is entitled to have it carried out by someone else at the contractor’s expense (contract sum)
If the instruction causes the contractor delay, it is possible for an Extension of Time to be claimed
What are the consequences of a certificate of non completion?
What can a CA do to open up and test works under JCT?
Issue an instruction for the opening up, inspection and testing of covered work, materials or goods.
The cost is added to the contract sum unless the work is not in accordance.
What must a CA provide to the contractor immediately after contract execution?
What is the Information Release Schedule?
States what information the CA will produce and when it will be provided - failure to provide on time is a Relevant Event / Matter for EoT / Loss and Expense
Can the CA suspend the contractor’s work?
Legally neither the employer nor CA has a legal right to order the contractor to suspend work, but in JCT the CA can issue an instruction to postpone the work - contractor is entitled to EoT and loss/expense.
Why might a variation be required?
1) Change in employer requirements
2) Client design development
3) Changes in legislation
4) Late information to contractor
5) Change in access
6) Change to materials or spec
7) Discrepancies between contract documents
8) Instructions to spend prime cost allowances or provisional sums
What is the definition of a variation?
Changes to;
What variations are not permissible?
Variations that go to the root of the contract
Can a contractor object to a variation?
Yes, the contractor has right to object on reasonable grounds to a variation which alters the working method
How are provisional sums expended?
The CA must issue an instruction for the expenditure of provisional sums
When does the Contract Administrator role commence?
Not until a building contract is in place between the employer and contractor.
In practice the Contract Administrator may be required to perform pre-contract services.
What is a major advantage of the impartiality of a Contract Administrator?
Their decision can be challenged by either the employer or the contractor.
An employer normally cannot challenge an Employer’s Agent decision.