What is a contract and what is a breach of contract?
Contract: Legally binding promise by one party to fulfil an obligation to another party in return for consideration. Must have key elements: offer, acceptance, consideration and intent to create legal relations.
Breach of contract: When one party in a binding agreement fails to deliver according to the terms of the agreement.
What is the difference between a procurement strategy, contract selection and tendering?
Procurement Strategy: Overall process of obtaining goods and services from a contractor, and strategy on how those goods/services are to be acquired by reviewing the employer’s requirements (time, cost, quality, responsibility for design) and their attitude to risk.
Contract Selection: Choice of appropriate contract flowing from analysis of employer’s requirements and the chosen procurement route.
Tendering: Bidding process and the actual process of appointing a contractor.
What are the key similarities and differences between JCT Minor Works and Intermediate contract types?
Similarities:
Differences:
What are the JCT forms suitable for a traditional procurement route?
Three main types:
1) Lump-sum contract: contract sum determined before the work is started
- JCT SBC with Quantities
- JCT SBC without Quantities
- JCT Intermediate / Minor Works, etc.
2) Measurement: contract sum determined after completion, but assessed on remeasurement on an agreed basis
- JCT SBC with approx. Quantities
- JCT Measured Term
3) Cost reimbursement: sum arrived at on the basis of actuals costs plus OH&P
- JCT Prime Cost
What are the main implications for the use of a JCT Intermediate over a JCT D&B contract?
Design:
Programme:
Administration:
Sub-contractors:
- Intermediate: provision for named sub-contractors
Cost Control (both fixed price, lump-sum):
Changes:
Warranty/Insurance/Novation:
- D&B: Collateral warranty, novated design team, PI.
What are the advantages of collateral warranty over third-party rights?
However;
- Takes time/cost to develop collateral warranties
What would be the implication of a contractor making design assumptions/decisions in traditional contracting?
What is a back-to-back contract?
Who shoulders what risk in traditional contracting?
Contractor risk:
Employer risk:
Who shoulders what risk in Design & Build?
Contractor risk:
Employer risk:
- Performance of main contractor
What are the differences between a bond and collateral warranty?
What are the differences between domestic, nominated and named sub-contractors?
Domestic: Chosen by the contractor, not influenced by the employer or employer’s consultants
Nominated: Not used much, no provision in JCT. Employer selects sub-contractor and imposes on contractor to appoint. Allowed for by a prime sum plus OH&P. Contract may not hold contractor entirely responsible for failure, employer might indemnify.
Named: Employer provides a list of pre-approved sub-contractors. Contractor selects one through the tendering process. Become domestic sub-contractors once appointed, i.e. contractor responsible for performance. PS included at tender, and replaced with actual price once agreed.
What are some of the considerations when selecting an appropriate construction contract?
1) Type of works required: Construction/engineering, new build/refurb, major/minor, specialist design, etc.
2) Sector: Familiarity of contract type, unfamiliar might cause contractors to price for risks.
3) Size, value and complexity: appropriate and proportionate in terms of risk balance and administrative burden.
4) Employer and level of sophistication: familiarity with contract type, level of administrative and decision-making capability
5) Balance of risk/risk allocation: risk allocation even within contracts designed for same procurement route
6) Design responsibility: some forms work with wide range of design responsibility (e.g. NEC), whereas others are procurement route specific (e.g. JCT D&B)
7) Control of sub-contractors: certain contracts allow greater control over selection, i.e. domestic vs named
What are the contracts in the JCT suite?
Traditional / lump sum
Traditional / measurement
Traditional / re-imbursement
- Prime Cost Contract
D&B:
Management / re-imbursement
Partnering / lump sum or target cost
- JCT Constructing Excellence Contract
When would you use a JCT Standard Building Contract?
1) Traditional procurement - design is complete, client retains design control and risk
2) Cost certainty - lump-sum (can also use re-measurement or reimbursement options)
3) Using BoQ (or approx. BoQ) or work schedules
4) Large or complex construction projects where detailed provisions needed
5) Options for:
- CDP
- Sectional completion
- Named specialists
- Bonds
- Advanced payment
- Third-party rights or collateral warranties
- Optional: fluctuations, BIM, collaborative working, sustainability
What are the main features of the JCT Design & Build Contract?
What is a loss and expense claim?
Common claims:
What is sectional completion under JCT?
What are the main options for insuring the works under a JCT contract?
Option A: Contractor takes out and maintains joint names all risks insurance of the works for new buildings
Option B: Employer takes out and maintains the joint names all risks insurance of the works for the new buildings
Option C: (Renovations) Employer takes out and maintains the joint names all risks insurance of the works and the policy also insures the existing structure and contents against ‘specific perils’ (fire, explosions, etc.)
What is contractor’s all risk insurance?
Protection against the physical loss or damage to the works being undertaken
Policy will pay for repair or replacement of the insured works following damage caused by an insured event
What are the key differences between JCT and NEC contracts?
Are you aware of any other forms of contract aside from JCT/NEC?
What are the relevant events in JCT?
What are the core clauses of an NEC PSC contract?