What is the difference between an Employer’s Agent and a Contract Adminstrator?
What are the key responsibilities of the contract administrator under a JCT contract?
What status does the programme have under a JCT and NEC contract?
What is Practical Completion?
Do the works have to be totally completed before practical / sectional completion is achieved?
Can you rescind a PC certificate once its been issued?
No
What is a non-completion certificate?
Issued by the CA to certify that works / section of works have not been completed by contractual completion date
What are the consequences of a non-completion certificate?
Process would be:
- Certificate of non-completion to be issued
- Employer must write to contractor to notify them they will be levying LD’s
- Employer would issue pay less notice to levy damages
What happens after PC is issued?
Under JCT, if the contract administrator believes completed works are not in accordance with the contract, what can they do to check / clarify?
Who bears the cost of opening up under JCT?
What is opening up called under NEC?
What is the definition of Extension of Time under JCT?
What is “time at large” under JCT?
What is the process for claiming an EOT?
Does an EOT give the contractor the right to additional preliminaries, under JCT?
No - this would be covered under Relevant Matters
What are payment provisions?
What are payment applications?
Received from the contractor, payment applications are an assessment of the amount the contractor believes is due for the works completed on site
What would you expect to be in a payment application?
Taking NEC4 Option A as an example:
- Activity Schedule
- Preliminaries and OH&P
- Advanced Payments (if applicable)
- Provisional Sums (if applicable)
- Schedule of Compensation Events
- Offsite materials / vesting (if applicable)
- Less retention (if applicable)
- Less previous assessments
- Net amount
What is the difference between payment notices and payment certificates?
Both are used to assess the amounts due to the contractor for the works completed to date
What is a payment notice / certificate?
A document issued to the contractor from the CA / PM to demonstrate the sum they consider due to the contractor at the DUE DATE, including all calculations for the amount
What is the due date?
The due date is 7 days after the valuation assessment date, in which is used to calculate all other dates associated with the payment cycle
Does the due date move?
What is a pay less notice?