What is a risk in the context of a construction project?
An uncertain event or set of circumstances that, should it occur, have a negative impact on the projects objectives
What is a risk assessment?
An assessment to identify the likelihood and severity a potential risk or hazard may have on a project
What is the difference between quantified and qualitative risk assessments?
What is the Monte Carlo simulation?
Uses computer software to predict the risk
Will run the project numerous times and each project will have a different outcome for each risk
This can then inform the risk register / allowances in order to manage risks more efficiently
What is a risk register?
A document listing all the risks identified on a project, explaining the nature of each risk in respect of quantitative and qualitative analysis
How do you go about creating a risk register for a new project?
How do you use the risk register?
What is risk allocation?
Can you name some risk management strategies and what they are?
What are the benefits of Risk Management?
Why is risk management needed in construction?
What is a risk allowance?
A sum of money in the estimate to cover unknown expenses, should they materialise
What are the NRM categories of risk?
How can the project team reduce design risk?
How would you calculate your risk allowance?
What are the problems associated with controlling the piling risk? Whose risk is the piling?
How is the risk register used in the post contract phase of a project?
-As the project progresses, some risks may have not materialised and the opportunity for them has passed.
-As the risk register is updated at intervals, as specified in the contract data, the risks that didn’t materialise will be omitted, and new risks may be added.
-This can then continuously update the contingency funds so the client understands their available funds, to enable them to make informed decisions
How do you quantify risk?
-For example, in my experience, one of the risks I identified was locating Asbestos in the building. Worst case scenario is Asbestos throughout the building, so let’s say £500 to remove the asbestos for the whole building of 2000m2 GIA gives £1,000,000 as a potential cost. But, I would then assign it a likelihood and impact factor. So, if it was discovered, it would be impactful to programme and cost, so it would be high (let’s say a 5). However, the likelihood would be high as the building was constructed post 2000 (lets say a 5 too). However, its unlikely the whole building will have asbestos throughout, so an assumption could be 50% coverage, so £500k would be included in the risk register
How do different procurement routes deal with risk? Can you give me some examples?
How is risk managed under an NEC contract?
-NEC utilise a collaborative, early warning system approach towards risks, which ensures either party makes the other aware of potential risks that could arise
- The use of early warnings and NCE’s give the client and contractor enough time to collaborate to reduce the impact of a risk, mitigate altogether, or agree to share etc.
In your submission you mention you were involved with identifying risks for CiNER Glass, one being for planning consent delays. Why did you identify this as a risk? What method of risk management did you propose for this, and how can you reduce the impact of planning consent delays?
For CiNER Glass, how did you suggest the discovery of an archaeological artefact is dealt with?
For the Kingsway, can you give an example of an Early Warning Notice and how the risk was controlled