Contract Administration Flashcards

(40 cards)

1
Q

What are the key differences between the role of an Employer’s Agent under JCT Design & Build and a Contract Administrator under JCT Standard Building Contract?

A

An Employers Agent is specific to a design and build contract and they act on behalf of the client by ensuring the contractor fulfils their duties.

A Contract Administrator oversees the contract by managing changes and ensuring contractual compliance.

A CA must remain impartial, whereas an EA does not as they’re acting on behalf of their client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Could you explain the payment notice procedures under the JCT Design & Build 2016 contract, including key timeframes and requirements?

A

The contractor will issue their application for payment on the set contractual date.

The due date is 7 days from the valuation date.

The payment notice must be issued within 5 days of the due date.

The final date for payment is within 14 days from the due date.

If a pay less notice is required, this must be issued at least five working days before the final date for payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would you explain the differences between FIDIC and JCT contract administration procedures to a client considering which contract to use?

A

FIDIC is internationally recognised and is commonly used for large-scale infrastructure projects.

The payment process in FIDIC is based on milestones, whereas in the JCT it is generally interim valuations.

Risk allocation in FIDIC is tailored to different project types, whereas in a JCT contract tends to put more onto the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between an Early Warning and a Variation under the JCT Design & Build contract, and how should each be administered?

A

Early warnings are used to highlight potential risks or issues that could impact the projects cost, time or quality.

Generally, early warnings do not have enough information to enable the contractor to price them so proactive communication is encouraged to avoid disputes.

A variation is a formal change to the contract scope and requires and instruction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between an EA and a CA.

A

An Employers Agent is specific to a design and build contract and they act on behalf of the client by ensuring the contractor fulfils their duties.

A Contract Administrator oversees the contract by managing changes and ensuring contractual compliance.

A CA must remain impartial, whereas an EA does not as they’re acting on behalf of their client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What under a JCT D&B constitutes a change?

A

Additions, Omissions or substitutions.

Instructions from the client.

Changes to access, working space or working hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In what circumstances, other than a change, might you need to issue an instruction under the contract?

A

A Provisional Sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you determine what constituted a change under the contract on the Vista Tower project, and what process did you follow when issuing Employer’s Agent Instructions?

A

I referred to section 5.1 in the JCT.

When issuing the Employer’s Agent Instruction, I ensured that the costs had been reviewed and agreed with the contractor. This was then presented to the client for agreement and sign off before the works commenced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the payment timeframe differences between a Design & Build and Traditional contract?

A

None, both contracts use the same payment timeframes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you do if there are discrepancies between the ER’s and CP’s?

A

Follow the contract and it’s amendments.

Ensure that the CP’s are followed forward and have an open discussion with the client and contractor to see if variations need to be raised.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a framework agreement?

A

It forms a long term arrangement between a client and a supplier.

The supplier is not guaranteed work, but it can streamline the tender process as the supplier will be pre-approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is nomination?

A
  • Selection of a particular subcontractor to carry out works, manufacture or supply of materials.
  • This provides the architect and client with greater control of material choice and thereby quality.
  • It is often used when there are long lead-in times with the employer placing orders prior to the Main Contract award which reduces potential delays on site.
  • The Main Contractor is relieved of liability of design and compliance with the performance spec in addition to subcontractor delays in respect of the works that have been nominated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Do nominated subcontractors get paid separately?

A

Nominated Contractors are normally paid via the Main Contract with sums identified separately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can the contractor object to a nominated subcontractor?

A
  • Any objections must be made during the tender period.
  • There are specific exclusions and grounds for an objection for example if they have found out the
    subcontractor is having financial difficulties and may be going insolvent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the employers payment responsibilities under the JCT contract?

A

Payments must be made to the contractor within the specified timeframes set out in the JCT.

I.e. the Final Date For Payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe differences between Statutory Provisions and Contract
Provisions?

A
  • Statutory provisions are set out by law & must be complied with.
  • Contract provisions relate to the contract in question & therefore only apply to a specific project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are domestic subcontractors?

A

This is a standard appointment of a Subcontractor by the Main Contractor.

18
Q

After a valuation and a certificate has been issued, the client advises you that they don’t have sufficient funding to make the payment. What would you do?

A
  • Once the certificate has been issued to the contractor, the client is contractually obliged to honour payment of the certificate and cannot withhold money without a valid reason.
  • If this were the case, I would contact the client and contractor ASAP to arrange some form of
    payment. It may be the case that the client has insufficient funds available in time for the final date for payment and it may be possible to defer payment by 1-2 days.
  • Failing this or if the contractor is unwilling to delay the payment, the client would need to find finance the payment through other funds to honour the certificate.
19
Q

If an instruction was issued during the contract which involved the fabrication of a substantial amount of materials off site would you pay for them as off site materials within the valuation?

A
  • There is no obligation on the client to pay for materials off site if this is not identified in the contract.
  • However in the scenario where the client wishes to pay for them, I would ultimately check with the client before paying or rejecting them.
20
Q

What documents would be required in incorporating a Contractor Design Portion Supplement into a project?

A

Within a Design & Build project, the documentation to be included would be the Employers Requirements including the Scope, Specification, Drawings, Contractors Proposals along with any insurances.

21
Q

Could an e-mail constitute a contract document?

A

Yes providing there is offer, acceptance, intention to create legal relations and the responding email does not vary the conditions, a contract will be created.

22
Q

What is a defined provisional sum?

A

A sum included in the contract for work that has not been completely designed at the time of contract sum agreement

Certain specified information can be given about the extent of works, its quantity, duration of installation and how it is to be fixed to the building.

23
Q

What is an undefined provisional sum?

A

A sum included for work for which there is minimal or no information at the time of contract sum agreement. The location, quantity and time associated for the installation of the works is not fully known.

24
Q

Can an EA act as a QS as well?

A

Yes, under a Design & Build Contract, an Employer’s Agent can also act as the Quantity Surveyor, provided that the scope of services is clearly defined and there is no conflict of interest.

Generally, it’s not advisable to do this.

25
What is an Employer's Agent?
A named individual or firm appointed by the employer to act on their behalf throughout the project. They're specifically used within Design & Build Contracts Although appointed by the employer, the EA must act impartially when administering the contract.
26
What is an Contract Administrator?
A named individual or firm responsible for administering the terms of the contract between the employer and the contractor. Used in a variety of JCT contracts, - Standard building contracts - Intermediate - Minor works - Prime cost CA's must act impartially and fairly when administering the contract.
27
What should an EA check following a payment recommendation?
That the works being claimed for have been undertaken and that they're in line with the ER's.
28
What type of instructions are there in a Design & Build?
Changes in the contract (variations, design changes). Partial posession. Access and site conditions (working hours, site access etc) Testing and opening up works.
29
How long do you have to agree a final account?
There are no fixed deadlines for agreeing the final account in a JCT, however there are key timeframes that guide the process. 1. The contractor must submit a final statement of account after practical completion 2. If the Employer disputes the final statement of account, they must provide a Notice of Dispute within 3 months
30
Can you carry out valuations after PC?
Yes, you can carry out valuations and make payments after practical completion.
31
Can you issue an instruction after PC?
It's not standard in a JCT. It could potentially be an amendment.
32
Can you grant an EOT after a non-completion certificate has been issued.
Yes.
33
What do you need to issue at the end of the Rectification Period?
Assuming all defects have been addressed then the Contract Administrator should issue the Certificate of Making Good.
34
What is a Non-Completion Certificate?
A certificate which is issued when the contractor has failed to complete the works by the completion date. It enables the client to claim LAD's.
35
What needs to take place for a client to claim LAD's?
A non-completion certificate needs to be issued. A payless notice is issued in the next interim application for payment equivalent to the LAD's stated in the contract.
36
What is a patent defect?
A defect which is obvious and can be spotted during snagging.
37
What is a latent defect?
A defect which is not discoverable by reasonable inspection. They can become apparent months or years down the line.
38
What section is payment in the JCT Design and Build?
Section 4.0.
39
What section is Change in the JCT Design and Build?
Section 5.0.
40
What section is Settlements of dispute in the JCT Design and Build?
Section 9.0.