Contract Administration Flashcards

(43 cards)

1
Q

What are your roles within JCT?

A

Under JCT Design & Build: You act as the Employer’s Agent (EA).

Under JCT Traditional: You act as the Contract Administrator (CA).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the role of the Employer’s Agent (EA)?

A

Used in JCT Design & Build contracts. The EA represents the employer but also administers the contract impartially.

Duties:

Issue instructions

Manage design approval (if retained by employer)

Certify interim and final payments

Assess and issue extensions of time

Inspect works and monitor progress

Certify practical completion and final account

Communicate between employer and contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the role of the Contract Administrator (CA)?

A

Used in JCT Traditional contracts. Usually an Architect, QS, or PM.

Duties:

Administer the contract fairly and impartially

Issue instructions (e.g. variations)

Inspect works and monitor progress

Assess EOTs and certify completion

Certify payments (interim and final)

Monitor defects liability process

Maintain clear records and manage contractual notices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the main difference between EA and CA?

A

CA (Traditional)
Oversees a contractor building to employer’s design
Usually not involved in design
Acts impartially

EA (Design & Build)
Contractor designs and builds
May manage retained design info
Represents employer’s interests (though still must act fairly)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do these roles differ from NEC?

A

NEC contracts have:

Project Manager (PM) role (not EA/CA)

PM manages the contract and gives instructions

PM assesses compensation events, issues early warnings

PM acts more proactively and collaboratively than CA/EA

There’s a Supervisor role for quality inspections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between Practical Completion and Sectional Completion?

A

Practical completion refers to the completion of the entire project and is when the project is handed over.

Sectional completion refers to the completion of pre-agreed parts of the project, each with its own completion date and potentially separate defect periods and LDs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between partial possession and sectional completion?

A

Partial possession is when the employer takes possession of part of the site during the works.

Sectional completion is when specific parts of the work are contractually agreed to complete on different dates.

Partial possession is flexible and initiated by the employer during the works; sectional completion must be written into the contract from the outset.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do you need in order to issue Practical Completion?

A

You must be satisfied that:

The works are complete and meet the contract requirements

There are no significant defects (only minor snagging may remain)

Health and Safety File is provided under CDM Regulations

All commissioning and certification are complete

The building is safe and fit for use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does CDM require the contractor to provide at completion?

A

The contractor must provide the Health and Safety File.
This includes as-built drawings, O&M manuals, manufacturer data, and any design risk assessments.
It helps ensure safe future use and maintenance of the building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does Practical Completion trigger?

A

End of liability for liquidated damages

Start of the defects liability period

Partial release of retention

Transfer of insurance responsibility

Start of final account negotiations

Occupation of the building (in most cases)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens if the contractor misses the contractual completion date?

A

The CA or EA can issue a Non-Completion Certificate, and liquidated damages (LDs) become payable by the contractor.
If no EOT is granted, the employer can deduct LDs as compensation for the delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are liquidated damages?

A

Liquidated damages are a pre-agreed daily or weekly amount payable by the contractor if they do not complete on time.
They are not a penalty but must reflect a reasonable estimate of the employer’s loss due to delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you give an example of how LDs might be calculated?

A

For example, if the employer has to rent temporary office space at £2,500 per week due to the delay, plus £1,500 in staff and management overheads, then LDs may be set at £4,000 per week.
This must be justified as a genuine pre-estimate of loss at the time of contract signing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the different types of damages related to delay?

A

Liquidated Damages (LDs): Pre-agreed in the contract

Unliquidated Damages: Calculated at the time of breach based on actual loss

General Damages: Assessed by the court when no LDs are specified

Consequential Damages: Indirect losses that may be excluded by contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What happens if no Non-Completion Certificate is issued and no EOT is granted?

A

In this case, Time becomes at large, meaning:

There is no enforceable completion date

The contractor is only obliged to complete within a “reasonable time”

The employer cannot enforce LDs, even if they’re in the contract

This is usually the result of the employer’s failure to follow proper procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Notice to Proceed?

A

A formal instruction to the contractor to start work, typically issued after conditions precedent (e.g. insurance) are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What happens at site possession?

A

The contractor takes official access to the site. The start date for the contract period usually begins from this date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are valuations and interim payments?

A

Valuations are assessments of the value of completed works (usually monthly). Interim payments are made to the contractor based on these valuations.

19
Q

How are changes managed under JCT?

A

Changes are issued as Architect’s Instructions (AIs) or Employer’s Agent Instructions (EAIs). Valued by the QS as variations.

20
Q

How are changes managed under NEC?

A

Changes are managed via Compensation Events, which must be notified, assessed, and agreed before implementation.

21
Q

What is the rectification (defects liability) period?

A

A fixed period (usually 6 or 12 months after Practical Completion) during which the contractor must return and fix defects identified.

22
Q

What is a Certificate of Making Good Defects?

A

A formal certificate issued after the contractor has remedied all notified defects, marking the end of their responsibility for defects.

23
Q

What is the Final Certificate?

A

This certifies that all contractual obligations have been completed, the final account is agreed, and the contract is closed.

24
Q

What is the Housing Grants, Construction and Regeneration Act 1996 (Construction Act)?

A

his Act governs construction contracts in the UK. Key provisions:

Right to interim payments

Payment notices and pay less notices

Statutory right to adjudication for resolving disputes quickly

25
What is adjudication?
A statutory dispute resolution mechanism under the Construction Act, allowing disputes to be decided quickly (usually 28 days) by an independent adjudicator.
26
What are Collateral Warranties?
Separate agreements that give third parties (e.g. funders, tenants) contractual rights similar to those under the main contract. Protect against privity of contract issues.
27
What is the Contracts (Rights of Third Parties) Act 1999?
This allows a third party (not a party to the contract) to enforce terms of a contract if: The contract expressly says they can, or The term benefits them
28
What are Third Party Rights (TPR)?
An alternative to warranties — allows third parties to enforce specified contract terms without needing a separate document, via the Contracts (Rights of Third Parties) Act.
29
What are CDM Regulations 2015?
Construction (Design and Management) Regulations 2015 relate to health and safety. They place duties on clients, designers, and contractors to manage H&S risks.
30
What is the Building Safety Act 2022?
Applies mainly to higher-risk residential buildings (HRRBs). Introduces: Accountable Person responsible for building safety Golden thread of digital information Stronger regulatory oversight (e.g., Building Safety Regulator)
31
What is an Interim Payment?
A payment made during the project based on the value of works completed to date.
32
What is Retention?
A percentage (usually 3–5%) withheld from each payment to ensure completion and remedy of defects.
33
What is a Certificate?
A formal document issued by the CA or EA to confirm events such as: Interim payment Practical completion Extension of time Final account agreement
34
What is the Rectification Period?
Also called the defects liability period — a defined time after practical completion for defects to be corrected by the contractor.
35
What is the Final Account?
The agreed final value of the contract, including all variations, loss and expense, adjustments to provisional sums, etc.
36
What is Adjudication?
A statutory dispute resolution process under the Construction Act that is: Fast (typically 28 days) Binding unless overturned in arbitration or litigation Used to resolve payment or delay disputes
37
What is an Early Warning in NEC?
A proactive notification of a matter that may affect time, cost, or quality. Required by both parties (Clause 15 in NEC4) Recorded in the Early Warning Register May lead to a risk reduction meeting
38
What is a Compensation Event in NEC?
A defined event (Clause 60) that entitles the contractor to extra time or money. Examples: Instruction to change the Scope Client delay in access to site Weather events beyond normal range PM accepting contractor’s proposal that alters the works
39
How is a Compensation Event managed?
Notification by contractor (within 8 weeks) Quotation for time/cost impact Assessment by Project Manager If accepted, Prices and Completion Date are updated
40
What is the difference between Early Warning and Compensation Event?
Early Warning Notifies a potential issue No automatic entitlement Preventative Logged in Early Warning Register Compensation Event Notifies a confirmed contractual event May lead to entitlement for time/money Reactive Logged in CE Register
41
What factors affect selection of a contract?
Value of project Size and complexity Design responsibility (client-led vs contractor-led) Client risk appetite Funding route (e.g. public or private sector) Procurement method (traditional, D&B, management) Programme and delivery priorities Familiarity of stakeholders with contract type
42
Give an example of a situation where JCT is more suitable than NEC.
A private residential development with full design complete before tender — JCT D&B is familiar, structured, and easier to administer.
43
Give an example where NEC is more suitable than JCT.
A complex infrastructure project with shared risks and evolving design — NEC provides flexibility, collaborative management, and better time/cost control.