What are your roles within JCT?
Under JCT Design & Build: You act as the Employer’s Agent (EA).
Under JCT Traditional: You act as the Contract Administrator (CA).
What is the role of the Employer’s Agent (EA)?
Used in JCT Design & Build contracts. The EA represents the employer but also administers the contract impartially.
Duties:
Issue instructions
Manage design approval (if retained by employer)
Certify interim and final payments
Assess and issue extensions of time
Inspect works and monitor progress
Certify practical completion and final account
Communicate between employer and contractor
What is the role of the Contract Administrator (CA)?
Used in JCT Traditional contracts. Usually an Architect, QS, or PM.
Duties:
Administer the contract fairly and impartially
Issue instructions (e.g. variations)
Inspect works and monitor progress
Assess EOTs and certify completion
Certify payments (interim and final)
Monitor defects liability process
Maintain clear records and manage contractual notices
What is the main difference between EA and CA?
CA (Traditional)
Oversees a contractor building to employer’s design
Usually not involved in design
Acts impartially
EA (Design & Build)
Contractor designs and builds
May manage retained design info
Represents employer’s interests (though still must act fairly)
How do these roles differ from NEC?
NEC contracts have:
Project Manager (PM) role (not EA/CA)
PM manages the contract and gives instructions
PM assesses compensation events, issues early warnings
PM acts more proactively and collaboratively than CA/EA
There’s a Supervisor role for quality inspections
What is the difference between Practical Completion and Sectional Completion?
Practical completion refers to the completion of the entire project and is when the project is handed over.
Sectional completion refers to the completion of pre-agreed parts of the project, each with its own completion date and potentially separate defect periods and LDs.
What is the difference between partial possession and sectional completion?
Partial possession is when the employer takes possession of part of the site during the works.
Sectional completion is when specific parts of the work are contractually agreed to complete on different dates.
Partial possession is flexible and initiated by the employer during the works; sectional completion must be written into the contract from the outset.
What do you need in order to issue Practical Completion?
You must be satisfied that:
The works are complete and meet the contract requirements
There are no significant defects (only minor snagging may remain)
Health and Safety File is provided under CDM Regulations
All commissioning and certification are complete
The building is safe and fit for use
What does CDM require the contractor to provide at completion?
The contractor must provide the Health and Safety File.
This includes as-built drawings, O&M manuals, manufacturer data, and any design risk assessments.
It helps ensure safe future use and maintenance of the building.
What does Practical Completion trigger?
End of liability for liquidated damages
Start of the defects liability period
Partial release of retention
Transfer of insurance responsibility
Start of final account negotiations
Occupation of the building (in most cases)
What happens if the contractor misses the contractual completion date?
The CA or EA can issue a Non-Completion Certificate, and liquidated damages (LDs) become payable by the contractor.
If no EOT is granted, the employer can deduct LDs as compensation for the delay.
What are liquidated damages?
Liquidated damages are a pre-agreed daily or weekly amount payable by the contractor if they do not complete on time.
They are not a penalty but must reflect a reasonable estimate of the employer’s loss due to delay.
Can you give an example of how LDs might be calculated?
For example, if the employer has to rent temporary office space at £2,500 per week due to the delay, plus £1,500 in staff and management overheads, then LDs may be set at £4,000 per week.
This must be justified as a genuine pre-estimate of loss at the time of contract signing.
What are the different types of damages related to delay?
Liquidated Damages (LDs): Pre-agreed in the contract
Unliquidated Damages: Calculated at the time of breach based on actual loss
General Damages: Assessed by the court when no LDs are specified
Consequential Damages: Indirect losses that may be excluded by contract
What happens if no Non-Completion Certificate is issued and no EOT is granted?
In this case, Time becomes at large, meaning:
There is no enforceable completion date
The contractor is only obliged to complete within a “reasonable time”
The employer cannot enforce LDs, even if they’re in the contract
This is usually the result of the employer’s failure to follow proper procedures
What is a Notice to Proceed?
A formal instruction to the contractor to start work, typically issued after conditions precedent (e.g. insurance) are met.
What happens at site possession?
The contractor takes official access to the site. The start date for the contract period usually begins from this date.
What are valuations and interim payments?
Valuations are assessments of the value of completed works (usually monthly). Interim payments are made to the contractor based on these valuations.
How are changes managed under JCT?
Changes are issued as Architect’s Instructions (AIs) or Employer’s Agent Instructions (EAIs). Valued by the QS as variations.
How are changes managed under NEC?
Changes are managed via Compensation Events, which must be notified, assessed, and agreed before implementation.
What is the rectification (defects liability) period?
A fixed period (usually 6 or 12 months after Practical Completion) during which the contractor must return and fix defects identified.
What is a Certificate of Making Good Defects?
A formal certificate issued after the contractor has remedied all notified defects, marking the end of their responsibility for defects.
What is the Final Certificate?
This certifies that all contractual obligations have been completed, the final account is agreed, and the contract is closed.
What is the Housing Grants, Construction and Regeneration Act 1996 (Construction Act)?
his Act governs construction contracts in the UK. Key provisions:
Right to interim payments
Payment notices and pay less notices
Statutory right to adjudication for resolving disputes quickly