Contract Practice Flashcards

(41 cards)

1
Q

What is a contract?

A

A legally binding agreement between two or more parties, enforceable by law, outlining obligations, rights, and responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do you need a contract?

A

To manage and allocate risk

Due to the complex and long-term nature of construction

Defines roles and responsibilities

Establishes legal recourse in disputes

Clarifies payment, timelines, quality, and performance expectations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is it important for the construction industry?

A

Complex projects with many parties involved

High value and long duration increase legal and financial risk

Prevents misunderstandings and disputes

Ensures legal enforceability of performance and payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What forms a contract?

A

Offer

Acceptance

Consideration (something of value exchanged)

Intention to create legal relations

Capacity to enter a contract

Legality of the contract’s subject matter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who drafts a contract?

A

Legal professionals draft contracts

As surveyors/project managers, we advise on suitability and risk but do not draft contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What if a client asks you to draft a contract?

A

You must not draft it

You can advise on:

Suitable contract forms

Key clauses (e.g. delays, variations, bonds, guarantees)

Direct the client to legal counsel for drafting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the ways a contract can be executed?

A

Orally (rare and not recommended in construction)

Under hand (simple written contract)

Under deed (signed, witnessed, and sealed – more formal)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the difference between under hand and under deed?

A

Under hand: signed only by parties, 6-year limitation period

Under deed: signed and witnessed, 12-year limitation period, no consideration required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the limitation period?

A

6 years for contracts under hand

12 years for contracts executed as deeds
Time limit to bring legal claims (e.g. breach of contract)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Other than limitation, what is a key difference?

A

Witnesses are required for a deed

Consideration is not required for a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the consequences of breaching a contract?

A

Damages/compensation

Termination of the contract

Dispute resolution (adjudication, arbitration, litigation)

Reputational and financial loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What factors influence contract selection?

A

Project size and complexity (large or small, simple or complex)

Design responsibility (who designs – client, contractor, or jointly)

Procurement route (traditional, design and build, management contracting)

Risk allocation preferences (how risks are shared or transferred)

Programme and delivery timelines (fixed, flexible, fast-track)

Client’s experience and familiarity with contract types

Funding and financial arrangements (public sector, private sector)

Level of collaboration required (traditional or partnering/collaborative)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What suites of contract are you familiar with?

A

JCT – Joint Contracts Tribunal

NEC – New Engineering Contract

FIDIC – International Federation of Consulting Engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Difference between JCT and NEC (consolidated)?

A

JCT
Traditional, adversarial
Emphasises legal clarity
Certainty through clear roles
Common in buildings
Slower to adapt to change

NEC
Collaborative, proactive
Emphasises project management
Flexibility with risk-sharing
Common in infrastructure/public
Regularly updated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pros/cons of standard form contracts:

A

✅ Pros:

Familiar across the industry

Cost-effective

Legally tested

Written by experts

❌ Cons:

May not suit bespoke needs

Can be ambiguous if heavily amended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Pros/cons of bespoke contracts:

A

✅ Pros:

Tailored to specific project needs

More flexibility

❌ Cons:

Not legally tested

Less familiar to parties

More costly to draft legally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Main structure of a JCT contract:

A
  1. Agreement
  2. Recitals
  3. Articles of agreement
  4. Contract particulars
  5. Attestation
  6. Conditions (Sections 1–9)
  7. chedules (e.g. insurance, CDP, warranties)
18
Q

What are the different types of contract?

A

Lump Sum

Target Cost

Cost Reimbursement

Remeasurement

19
Q

What is a Lump Sum Contract?

A

Fixed price for defined works

Contractor takes design and quantity risk

Used when scope is clear

20
Q

What is Remeasurement Contract?

A

Final price based on actual quantities measured

Common where scope is not fully defined at contract stage

21
Q

What is a Target Cost Contract?

A

Parties share cost savings/overruns against a target price

Encourages collaboration and cost control

22
Q

What is a Cost Reimbursement Contract?

A

Contractor is reimbursed for actual costs plus a fee

Suitable for emergency works or unknown scopes

23
Q

What JCT contracts are you familiar with?

A

JCT Design & Build (D&B)

JCT Standard Building Contract (SBC)

JCT Intermediate Building Contract (IC)

JCT Minor Works

24
Q

Difference between JCT Minor Works and JCT Design & Build?

A

JCT Minor Works
Simple, low-value projects
Employer provides full design
Minimal admin

JCT D&B
Complex, larger projects
Contractor takes on design responsibility
High contractor risk, less employer control

25
When would you use JCT Intermediate Building Contract?
Medium-sized projects Some design complexity Employer-led design When Minor Works is too basic, but SBC is too complex
26
What NEC contracts are you aware of?
NEC4 Engineering and Construction Contract (ECC) NEC4 Professional Services Contract (PSC) NEC4 Term Service Contract (TSC) NEC4 Framework Contract
27
How is an NEC contract formed?
Core Clauses Main Options (A to F) Secondary Options (X-clauses) Contract Data, Scope, Site Information Optional Z-clauses (amendments)
28
Talk through NEC Main Options:
Option Type A Priced contract with activity schedule (lump sum) B Priced contract with bill of quantities (re-measured) C Target contract with activity schedule D Target contract with bill of quantities E Cost reimbursable F Management contract
29
Example of NEC Main Option?
Option C – Used for complex, collaborative projects with cost transparency and shared risk
30
Example of NEC Secondary Options (X-clauses)?
Option Purpose X1 Price adjustment for inflation X2 Changes in law X7 Delay damages X16 Retention X18 Limitation of liability X20 Key performance indicators (KPIs)
31
What is a Performance Bond?
A Performance Bond is a security provided by the contractor’s bank or insurer guaranteeing that the contractor will perform the contract according to its terms. If the contractor defaults, the bond can be called upon to compensate the employer.
32
What is a Parent Company Guarantee (PCG)?
A PCG is a guarantee from the contractor’s parent company ensuring that the contractor’s obligations will be fulfilled. It provides the employer additional security, especially if the contractor is a subsidiary.
33
What are warranties in construction contracts?
Warranties are contractual promises about the quality or performance of works, materials, or services. They may be given by contractors, suppliers, or designers and often provide remedies if defects or failures occur.
34
What types of insurance are commonly required?
Typical insurances include: Contractors’ All Risks (CAR) Insurance – Covers loss or damage to works during construction. Public Liability Insurance – Protects against injury or damage claims from third parties. Employer’s Liability Insurance – Covers injury to employees. Professional Indemnity Insurance – For designers/consultants against design errors. Decennial Liability Insurance – In some countries, covers defects over a 10-year period.
35
Why are these securities and insurances important?
They provide financial protection against risks such as contractor default, defects, accidents, or damage during construction, safeguarding the employer’s interests.
36
What is a collateral warranty?
A collateral warranty is a separate legal agreement given by a contractor, consultant, or subcontractor to a third party (often the employer’s funder, tenant, or purchaser) that extends the original contract’s rights and obligations to that third party.
37
Why are collateral warranties used?
They provide third parties who are not part of the original contract direct rights to enforce the contractor’s or consultant’s obligations, especially regarding defects, performance, and liability. This is important when the employer has transferred the building or when financiers or tenants want contractual protection.
38
How does a collateral warranty differ from the main contract?
While the main contract is between the employer and the contractor/consultant, the collateral warranty creates a separate, parallel contract between the contractor/consultant and the third party, often mirroring key terms of the main contract.
39
Why is a collateral warranty important in practice?
It allows third parties to have direct recourse against designers, contractors, or consultants if there are defects or failures, without needing to rely on claims through the employer, thus providing greater protection and certainty.
40
What are Pre-Construction Services Agreements?
Pre-Construction Services Agreements (PCSAs), sometimes referred to as Pre-Contract Services Agreements, enable clients to employ contractors before the main contract for the construction of the works has been awarded. Typically they are part of a two-stage tender process, used in the first stage to procure contractor involvement in the design process, where the second stage procures the construction of the project.
41
Early appointment of the contractor under a Pre-Construction Services Agreement can allow them to?
Contribute to the design process. Advise on the buildability, sequencing, and risk of the construction works. Advise on the packaging of the works for sub-contractors and suppliers (and the risks of interfaces between packages). Advise on the selection of specialist contractors. Help develop the cost plan and construction programme. Help develop the method of construction. Obtain prices for work packages from sub-contractors or suppliers on an open book basis. Prepare a site layout plan for the construction stage showing temporary facilities. Draft the preliminaries for specialist and trade contractor bid documents. Assist with any planning application on matters concerning the build phase, such as; waste disposal proposals, construction traffic movements, tree preservation protection, etc.