When woud you use JCT Minor works and when wouldnt you?
JCT Minor Works contract selection criteria. We have learnt that the JCT Minor Works contract is commonly used for projects likely to be administered by a building surveyor under the traditional procurement method – and it is under the following criteria: • Where the work involved is simple in character. • Where the work is designed by or on behalf of the client/employer. • Where the client/employer is to provide drawings and/or a specification and/or work schedules to define adequately the quantity and quality of the work; and • Where an architect/contract administrator is to administer the conditions. • Where the approximate maximum value is £500k – but this is flexible depending on the complexity of the project. It is not however suitable: • Under a design and build procurement route as a design and build contract. • Where bills of quantities are required. • Where provisions are required to govern work carried out by named specialists. • Where detailed control procedures are needed. Slide 32
What are the articles of agreement?
Articles of agreement This section identifies the key parties to the contract and other stakeholders. This section identifies the various stakeholders linked to the contract including: • The two parties to the Contract – ie. Client/Employer & Contractor • Architect/Contract Administrator • Quantity Surveyor • CDM Principal Designer • Principal Contractor • Other professionals
What are the contract particulars
Contract Particulars This section contains the all-important contract clauses covering items including: • Carrying out the works • Control of the works • Payment • Injury, damage and insurance • Termination • Disputes
What is section 2 of the JCT MW?
Section 2 – Carrying out the Works - Contractor’s Obligations - Extension of Time It is extremely important that the building surveyor has a firm grasp of the following clauses and concepts as they are most likely to be the source of disputes when administering a contract. Contractors obligations The contractor is basically required to carry out the specified works to the requisite quality within the agreed timescale. It is the Contract administrators responsibility to check the quality of the work completed during regular site progress inspections. Possession of site It is important that the site is made fully available to the contractor by the client on the agreed date in order for him to mobilise his operations and commence work to meet the agreed programme of work. Failure by the client to release part or all the site could constitute a breach of contract and justify an extension of time for the contractor. Errors, Discrepancies and Divergencies Errors within the design documentation are often discovered once the contractor has started on site (eg divergence between the specification and drawings due to a limited design timescale) and this section covers how they are to be dealt with. Extension of time This is often a contentious issue as a contractor will often apply for an extension of time as a result of delays to their original programme for various reasons – and it will be the contract administrator’s decision on whether to approve or decline it. The general rule is that an extension of time should only be issued if the reason is ‘outside of the contractors control’ – otherwise known as ‘A relevant event’ which potentially include: • Weather – If the work or part thereof is external • Force majeure – An Act of God • Additional work instructed by the client – This is most common • Others including the client failing to provide the contractor with reasonable access or information Section 2.1.1 – Contractors obligations: ‘The Contractor shall carry out and complete the works in a proper and workmanlike manner and in compliance with the Contract Documents, the Construction Phase Plan and Statutory Requirements, and shall give all notices required by the Statutory Requirements’.
When would an extension of time be granted to the contractor and what is considered a ‘relevant event’?
WAFA - Weather, Additional, Force, Access The general rule is that an extension of time should only be issued if the reason is ‘outside of the contractors control’ – otherwise known as ‘A relevant event’ which potentially include: • Weather – If the work or part thereof is external • Force majeure – An Act of God • Additional work instructed by the client – This is most common • Others including the client failing to provide the contractor with reasonable access or information
What does practical completion trigger?
The final months payment (known as the Penultimate Payment). • Release of the contractors insurance obligations (which may be expensive). • Exemption of the contractor’s liability to pay Liquidated damages. • Half the retention is released • Start of the ‘Rectification Period’.
What is the rectification period?
The Rectification period is normally a period of 3, 6 or 12 months where the contract remains ‘open’ after practical completion of the work during which the contractor is still liable for rectifying problems (or defects) which have developed following the building work.
What are liquidated damages
LDs are sum of money included within the contract to incentivise the contractor to complete on time … and may be deducted from the contractors final monthly payments and retention (see retention later). LDs are a reasonable estimate of loss as a result of the project not completing on time (for example £250 per week due loss of rent of a residential property).
What are defects?
Defects are the legal term for work which has not been completed to the agreed specification or work that has subsequently failed whilst still under contract.
What is the certificate of making good?
This certificate (and also the certificate on ‘Not making good’) need to be completed by the contract administrator following rectification/failure to rectify defects … and certifies their rectification or otherwise. These will either trigger the ‘Final payment’ to the contractor or result in withholding money until they are rectified.
When should the PC date be decided?
It is important to be aware that the Practical Completion date will be included within the contractors construction programme which should be tabled at the pre contract meeting.
What is on an agenda for a pre-contract meeting?
A standard agenda for a pre contract meeting will cover issues including: Health and safety Access arrangements Storage Programme Valuation and payment arrangements Site progress meetings Project insurance Person in charge AOB
Can you explain clause 2.8.1 damages for non completion?
Section 2.8.1 – Damages for non completion ‘If the works are not completed by the Date for Completion stated within the Contract Particulars, or as later fixed under clause 2.7, the Employer may require the Contractor to pay or allow to the Employer liquidated damages at the rate stated in the Contract Particulars between such Date for Completion and the date of practical completion’ It is critical that LDs within a contract are set at a realistic level – they are an excellent tool for encouraging the contractor to adhere to their programme.
What is an instruction under the contract? Can they be verbal?
These are formal documents issued by the contract administrator to document ANY communication between the CA and the contractor. There are many standard instruction forms available for a CA to use. An instruction can range from a single page of A4 to detailed documentation including drawings and specifications if additional work is being instructed. Also – see the following slide. Section 3.4 – CA instructions ‘The Architect/Contract Administrator may issue instructions and the Contractor shall forthwith comply with them. If instructions are given orally, they shall not have effect until the Architect/Contract Administrator confirms them in writing’. There may be numerous instructions issued – ensure you keep up to date with your records.
What is a provisional sum?
A provisional sum is a figure specified within the tender and contract documents which is included to fund an item which cannot be fully specified prior to work commencing for various reasons. An example would be an inclusion of £10,000 to cover provision of new foundations which cannot be specified due to the uncertainty of the ground conditions. The contractor will then be required to complete the work within that sum – therefore the sum included should be adequate
What is clause 3.2 of JCT MW person in charge inreference to?
Section 3.2 – Person in charge: ‘The Contractor shall ensure that at all reasonable times he has on the site a competent person in charge. Any instructions given to that person by the Architect/Contract Administrator shall be deemed to have been issued to the Contractor’.
What is a contract instruction and what should it contain?
A contract instruction is an important legally binding document and may well be referred to in any disputes or legal action which may arise between the client and the contractor – so it is essential that the CA ensures the format and content of the document is accurate and compliant with legal protocol The format should be as follows (in writing but can be verbal initially): • Names of the parties involved • Include the Project Name • Specify the Date • Provide an issue number • Circulate to all necessary parties • Quantify the financial implication • The content of instructions will include the following: • Only what the contract states e.g. • Variation of the works • Removal of work not in accordance with the contract • Expenditure of Provisional Sums • Opening up of the works for inspection/testing The content of instructions will include the following: • Only what the contract states e.g. • Variation of the works • Removal of work not in accordance with the contract • Expenditure of Provisional Sums • Opening up of the works for inspection/testing
Can you explain what the contract sum means?
Contract Sum The ‘Contract Sum’ is the agreed lump sum the client will pay the contractor for the work. This figure will quite often be subject to change (normally an increase) and this will then become the ‘Final Account’ figure.
What certificates might the contract administrator be required to issue under the contract?
The CA will be required to issue a number of certificates. Why are Certificates issued? • Confirmation of certain events, milestones and occurrences eg. • Practical completion • Making good of defects • Partial possession • Making good to relevant part • Non-completion • Payment certificates.
What are interim payment certificates?
The CA will normally issue interim ‘payment certificates’ to the client on a monthly basis following receipt of the contractors invoice. This is effectively a formal instruction to pay the contractor within a certain period. The CA will first check the validity of the contractors invoice against the contractors programme in conjunction with the design information.
What are the penultimate payment and the final payment?
The Penultimate payment is made at Practical completion stage and the Final payment is made after the Rectification period (see below).
What is the retention?
Retention This is a sum of money the CA deducts from each monthly payment which may be released back to the contractor in various stages. A typical figure is 5% of the agreed sum to be paid therefore the contractor receives only 95% of the value of the completed work. This money is held back from the contractor as an incentive to complete the project on time – and to rectify defects during the rectification period – as 2.5% of the 5% is released at ‘Practical Completion’ and 2.5% is released after the rectification period. The final payment is made at the end of the rectification period once the CA has completed the ‘Making good of defects’ certificate.
What are the payment terms?
Payment terms The payment terms specify the frequency and dates by which the Client must pay the Contractor for the work carried out – and also the penalty for late payment by the client. Cash flow is extremely important for both parties to the contract but in particular the contractor as he is likely to have a supply chain below him to remunerate
Can you explain clause 4.3 interim payments under JCT MW?