What will the choice of procurement strategy be dictated by?
Name five types of procurement route
1) Traditional
2) Design and Build
3) Management Contracting
4) Construction Management
5) Partnering
What is involved in a traditional procurement route?
Client appoints a design team who design the works, and produce the tender information (including drawings, schedules etc.). Contractors are then invited to tender for the works, normally on a single-stage, competitive basis.
Therefore the design is separate from the construction, with little to no design responsibility with the contractor.
What are the advantage of a traditional procurement route?
What are the disadvantages of a traditional procurement route?
What is involved in design and build as a procurement route?
The contractor holds design and construction responsibility.
Client novates their design (or design team) to the contractor. At some point the employer will submit their “Employer’s Requirements”. CA is an Employer’s Agent.
What are the advantages of design and build as a procurement route?
What are the disadvantages of design and build as a procurement route?
What is an Engineering, Procurement and Construction contract?
Sometimes referred to as a Turnkey Contract. They are similar to D&B in that there is a single contract for the design and construction of the project. However, an EPC contract will likely have less client input and control over the design, and the contractor will take on more risk.
What is involved in management contracting as a procurement route?
Management contracting involves the appointment of a “management contractor” who procures individual works contracts for different packages of works. They are generally appointed at an early stage to allow input into design and buildability.
What the advantages of management contracting as a procurement route?
What are the disadvantages of management contracting as a procurement route?
What is the difference between management contracting and construction management as procurement routes?
What is involved in construction management as a procurement route?
All works are constructed by different trade contractors. All of these trade contracts are are contracted directly to the client and are managed by a construction manager. The construction manager is not contractually linked to the trade contractors, but instead acts as an agent for the client, administering and coordinating the works contractors.
What are the advantages of construction management as a procurement route?
What are the disadvantages of construction management as a procurement route?
What is involved in partnering as a procurement route?
Partnering is a broad term used to describe a collaborative management approach to management, aims to encourage openness and trust between parties in a contract. Inspired by the 1994 Latham Report.