What are the varying types of forms of contract available in the market place?
When would design and build be used in comparison to a traditional form of contract?
What are the benefits of Design & Build?
What are the disadvantages of using this form? (Design and build)
How do you deal with assignation clauses?
What types of Damages are you aware of?
What types of bonds are available for construction projects?
What is an advanced payment bond? How does this work in practice?
The advanced payment bond may be required when the client agrees to make an advance payment to the contractor to secure the payment against default by the contractor.
For example, on NCA project, the Client agreed to make an advanced payment bond to the contract due the high cost of materials that had to be pre-order (lifts). In this case the advanced payment was approx. 20% of the construction work value. The advanced payment bond prepared together with the contract documentation and signed between the Client, the Contract and guarantor (executed as deed).
Can you outline the key changes under the introduction of NEC4?
What does assignment in contracts means?
On the NCA Spring Gardens project, what was included in the
contract documentation you prepared?
On NCA Contract documentation included:
What were the contract options you advised on?
On NCA I advised the Client regarding different Main Option under NEC suite of contract that you could be incorporated and its consequences. My advice include recommendation with regards to risk allocation, payment mechanism and documentation required for each option.
What were the “other documents required” you mention? (NCA)
Appart form the Works information the following document were included in Contract Documents for NCA Spring Gardens Project:
What are the risks from using a bespoke form of contract?
How did you assess the figure to be included for L&A damages on
a contract?
My projects:
Why are Liquidated and Ascertained damages included in a
contract?
What happens if it’s left blank in a signed contract?
The Client may not be entiteled to liquidated as well as unliquidated damages.
What was the change procedure under the Project Winchester
contract?
What happened if it was not adhered to? (change control)
What was the process under the contract for carrying out the
interim valuations?
On Project Winchester the interim valuation process was as follow:
What would have been the consequences had you not acted
within the contract valuation timelines?
What was the final account procedure under this contract? (Project Winchester)
RICS guidance on Final account procedures explained the procedures for different types of contract.
What was the procedure under this contract for notifying delays?
In order to prove a delay claim under NEC3, a contractor must follow a two step-process to show that (i) a compensation event has occurred; and (ii) that this event caused a delay to the completion of the project.
What would be included within a Letter of Intent?
A letter of intent is a document expressing an intention to enter into a contract at a future date but creates no contractual relationship until that future contract has been entered into. A letter of intent is not an ‘agreement to agree’.
A comprehensive letter of intent should address the following: