What if the client tells you the LADs are to be £100,000 per week?
I would check that the LAD figure is based on a genuine pre-estimate of financial loss and explain that
in the event LAD’s are to be applied, they would need to substantiate this figure.
* I would also explain that if the figure inserted into the contract is shown to be punitive and not based
on genuine financial loss it is not likely to be enforceable.
* In this scenario the employer will have to pursue the Main Contractor for any actual direct loss that can
be substantiated through a formal dispute resolution procedure.
What are extensions of time?
What are liquidated damages?
What must be in place before Liquidated Damages can be deducted?
What if the employer actually suffered no loss or damage?
What are the benefits of being able to grant an extension of time?
What happens when ‘time is at large’?
What are Relevant Events in a JCT form of Contract?
What are the relevant events?
There are 13 relevant events set out in JCT forms including:
o Variations.
o Instructions.
o Execution of an approx. quantity that is not a reasonably accurate forecast.
o Deferment of possession of the site.
o Suspension by the contractor for non-payment.
o The carrying out of work by statutory authorities.
o Impediment, prevention or default by the employer.
o Loss or damages occasioned by the Specified Perils.
o Exceptionally adverse weather conditions.
o Strike or lock out.
o Civil commotion or terrorism.
o The exercise of any statutory power after the base date by the UK gov.
o Force majeure.
What are the main elements you would include within an interim
valuation?
What needs to be in place for you to include payments for materials on
site?
The materials should be for the works.
* They should be adequately protected.
* Delivered to programme.
* In a reasonable quantity
What needs to be in place for you to include payments for materials
off site?
What is a retention of title clause?
How do you evaluate interim valuations?
How do stage payments work?
What is the interim certificate conclusive of?
What is retention?
It is a percentage of each interim certificate deducted and retained by the employer from each interim
payment to the contractor.
What is the purpose of retention?
When is the retention released to the contractor?
What is a typical retention percentage under JCT contracts?
What is a retention bond?
What happens if the contractor does not maintain the retention bond?
Why might a retention bond be used?
It may be used in difficult market conditions to aid the contractor’s cashflow
What are the disadvantages of a retention bond?