Why were the New Rules of Measurement introduced?
What is the structure of the NRM 1?
The key sections of NRM1 are:
o Part 1: General introduction explaining the purpose of the document and how it should be
used.
o Part 2: Measurement rules for the production of order of cost estimates.
o Part 3: Measurement rules for the production of elemental cost plans.
o Part 4: Tabulated rules of measurement for elemental cost planning.
o Appendices: With references to the definitions for GIA, functional units, NIA, elemental
breakdowns, templates and general information required for cost plan production.
Why should you use the New Rules of Measurement?
What are the NRM 1?
What is meant by the abbreviation GEA?
What is meant by the abbreviation GIA?
What is meant by the abbreviation NIA?
Where are all of these abbreviations defined?
What is the purpose of the Code of Measuring Practice?
The Code of Measuring Practice provides precise definitions to permit the accurate and consistent
measurement of buildings
What would you expect the percentage of NIA to GIA to be?
What do you measure in accordance with?
How do you measure structural steelwork under NRM 2 and what
other items would you measure in association?
How do you measure brickwork walls under NRM and what other
items would you measure in association?
What is the purpose of a BoQ?
How would you prepare a BoQ?
How would you structure a BoQ?
In accordance with an elemental breakdown structure under NRM 2, I would include the following
sections:-
o Preliminaries (Main Contract).
o Facilitating Works.
o Substructure.
o Superstructure.
o Internal Finishes.
o Fittings, Furnishings and Equipment.
o Services.
o External Works.
o Provisional Sums.
o Dayworks
How would you describe the preliminaries section in a Bill of
Quantities?
What information is required to measure preliminaries?
Contract duration.
* Location.
* Type of project (New Build vs. Refurb).
* The size of the project.
* Temporary works.
* Security.
* Methodology.
* Programme.
* Services.
* Employers accommodation.
* Contractor designed work.
* Sectional completion.
* Insurances / Bonds
If it was found that a Bill rate was blatantly wrong for example £100
was included as a rate instead of £1, how would this be resolved?
How do you evaluate a variation which is based on a BQ item which
contains an error?
Who owns the copyright to a BQ?
How would you deal with a situation where it was discovered a part of
a BQ was missing after the Main Contractor was on site?
What would you include within the BoQ where works are to be carried
out by Nominated Subcontractor?
What is a Provisional Sum?