What is the difference between JCT 2016 suite and JCT 2024?
What is a contract administrator
What is the role of a CA
Precon:
- Aid prep of contact docs
- inviting and processing tenders
- aiding tender analysis and negotiation
- Preparing contract documents for execution
Postcon:
- issue of certs - payment notices, PC, Sectional completion
- Seeking approval for and issuing instructions such as variations
- Considering claims for L&E, EOTs
- Chairing meetings
- Defects schedule and making good
What is an Employer’s Agent
What is the role of the EA
Similar role to a CA
What is the difference between a CA and EA
What are the different JCT Suites of Contract
1) Standard Building Contract
2) Minor Works Contract
3) Intermediate Building Contract
4) Design and Build Contract
5) Major Project Construction Contract
6) Construction Management Contract
7) Management Building Contract
etc…
What are the different types of the standard building contract
What Key project characteristics influence which JCT is used
When would you use a JCT Minor Works Contract
When would you use a JCT Intermediate Contract
When would you use a JCT Standard Building Contract WITH Quantities
When would you use a JCT Standard Building Contract WITHOUT Quantities
When would you use a JCT Standard Building Contract with approximate quantities
When would you use a JCT Major Works
When would you use a JCT Design and Build
What does NEC Stand for
When would you use a New Engineering Contract
What are the different contract options under New Engingering Contracts
Option A: Priced Contract with activity schedule
Option B: Priced contract with bill of quantities
Option C: Target Contract with Activity Schedule
Option D: Target Contract with Bill of Quantities
Option E: Cost reimbursable contract
Option F: Management Contract
What is a bill of quantities
A Bill of Quantities is a detailed document to itemize everything needed to complete the work.
What are the main differences between NEC and JCT Contracts
What are listed items
Where can you find the procedure for materials off site
How do you value materials off site