Contract Practice Flashcards

(29 cards)

1
Q

What is a collateral warranty?

A

A legal document that creates a contractual link between a third party and a party in a construction contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are collateral warranties used for?

A

To bridge the gap between parties and allow a third party to make a claim if something goes wrong

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is meant by the privity of contracts?

A

Only the parties that have entered into a contract can enforce or are bound to it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the JCT Valuation rules

A
  • Contract rates
  • Adjusted contract rates
  • Fair and reasonable
  • Dayworks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a relevant event?

A

An event that is not the contractors fault that causes a delay to the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a relevant matter?

A

Something that causes the contractor additional costs such as a client driven change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are LDs?

A

A genuine pre-estimate of the likely cost to the employer when the practical completion date is not met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do you need before deducting LDs?

A
  • A non-completion certificate
  • A withholding notice
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What needs to be in place to pay for materials on site?

A
  • materials should be purchased for the works
  • vesting cert
  • insurance
  • EA can inspect
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What needs to be in place for materials off site?

A
  • Vesting certificate
  • Insurance until materials arrive on site
  • Materials are clearly labelled for the site
  • Materials off site bond if required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a materials off site bond?

A

It is a bond to ensure that if the materials cant be delivered then the full amount paid is returned to the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a retention of title clause?

A

Sub-contractor or supplier retains ownership of materials until they are paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the typical retention % for a SBC?

A

3%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the typical retention % for D&B?

A

5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the different certificates you’re aware of under JCT?

A
  • Interim certificates
  • Practical completion or sectional completion
  • Non completion
  • Certificate of making good
  • Final certificate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the three ways benefits can be transferred under JCT contracts?

A
  • Collateral warranties
  • Third party rights
  • Assignment
17
Q

What is assignment?

A

Where the rights and benefits of one contractual party are transferred to a third party

18
Q

What is novation?

A

Where a new contract transfers the rights and obligations of one contractual party to a new third party

19
Q

How does novation differ to assignment?

A

Assignments only transfer contractual rights or benefits not burdens.

20
Q

What is a letter of intent (LOI)?

A

An letter issued to commence works with the agreement to enter into contract at a later date

21
Q

What are the key differences between JCT and NEC?

A
  • Programme is a contractual document in NEC
  • NEC uses compensation events rather than variations
  • NEC is project manager led
  • JCT uses valuations whereas NEC uses a priced activity schedule or defined costs
22
Q

What relevant events allow for additional time and money?

A
  • Variations
  • Late information
  • Employer delay (deferment)
  • Employer instruction to suspend works
  • Discrepancies in contract documents
  • Employer prevention of the works ongoing
23
Q

What is insurance?

A

Transfer of a defined risk to a company for a premium

24
Q

What is indemnity?

A

It is to protect against legal responsibility or to compensate

25
What is a tender bond?
Protects the party inviting the tender if the lowest tender refuses to go into contract
26
What is a parent company garuntee?
An arrangement where the performance of a company in a corporate group is underwritten by another company within the group
27
What is JCT Insurance Option A?
Contractor takes out 'All Risk' Insurance policy covering all works
28
What is JCT Insurance Option B?
Client takes out 'All Risk' Insurance policy cover all works - Can be difficult for the client to get comprehensive cover for construction works
29
What is JCT Insurance Option C?
It is for projects involving existing structures. Client takes out two joint name policies, one covering existing structure and its contents from specified perils and an 'All Risks' policy for the works themselves