Contract Practice Flashcards

(14 cards)

1
Q

What is an early warning?

A

An early warning is a formal notification by the contractor or consultant to the client when an event is identified that could affect cost, time or quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does an early warning work?

A

1) Contractor identifies a risk or potential issue
2) Contractor sends early warning notice to the PM
3) PM records in EWR
3) Project team then discusses mitigation measures to reduce risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why are early warnings important?

A

1) Prevents problems escalating and encourages collaboration between contractor and project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a compensation event?

A

A compensation event is an event that entitles the contractor to additional time or cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an example of when a compensation event may occur?

A

1) Change in client requirements
2) Design errors
3) Unexpected site conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does a compensation event work?

A

1) Contractor identifies an event that could be a CE
2) Contractor submits a quotation to the PM
3) Contractors submission may be commercially evaluated by QS and PM
4) The PM then reviews, assesses and certifies any entitlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is another key mechanism of the NEC contract?

A

Programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why are compensation events important?

A

1) Ensures contractor receives fair compensation when change or risks occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is the programme mechanism conducted?

A

1) Contractor submits programme
2) Programme is reviewed/accepted by PM
3) Contractor regularly updates the programme to reflect progress, delays or change
4) The programme is used to assess compliance with the completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is the programme important?

A

1) Provides a baseline for time management
2) Supports the planning of resources and plant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is the scope of works applied at different stages of a project?

A

1) It helps define the project brief and project feasibility
2) It can help refine drawings and specifications
3) It serves as the baseline for monitoring work, assessing completion and managing change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is contract data applied at different stages of a project?

A

1) At the award of the contract, it defines milestones and responsibilities
2) During construction it is used to monitor progress and payments, calculate compensation events and assess compliance with contract terms
3) During final accounting, it provides reference for retention release and contract completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are examples of NEC Option Clauses? A-F

A

A - Priced contract with activity schedule
B - Priced contract with bill of quantities
C - Target contract with activity schedule
D - Target contract with bill of quantities
E - Cost reimbursable contract
F - Management contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of different option clauses?

A

The option selected on a project defines how the contract handles payments, risks and incentives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly