What are the different forms of standard building contract available in the UK?
JCT
NEC
FIDIC
Where are the different contract suits commonly used?
What is the JCT and what are their suite of contracts?
Joint Contracts Tribunal, formed in 1931 Suit of Contracts includes: • Standard (with quants, without, with approx.) • Intermediate • Minor works • Design and Build
What are the advantages with a standard form of contract? How is it formed?
The advantages of a Standard Building Contract include:
• Developed over a long period
• Has input from legal, client, contractor, local authority
• Has more case law
• Less costly and time consuming to produce than a bespoke contract.
• Guidance notes available
What is an intermediate Contract?
What is included in a payment notice?
What are the timelines for payment? Where can this information be found?
What is Practical Completion? What does it Trigger?
• When all works in the contract have been deemed to be completed and the client can take occupation.
- The point at which a building project is complete, except for minor/ de minimis defects that can be put right without undue interference or disturbance to an occupier.
- The contractor has complied with clauses 2.37 and 3.16
• It releases half of the retention
• Ends the contractor’s liability for LD’s
• Starts the defects liability period
- The client to carry out its own FRA.
What documentation is required at PC?
What is sectional completion and what is partial possession?
What are staged payments?
What is the interim payment process? Where is this specified in the contract?
What guidance documents are available?
* JCT – Guide to selecting the appropriate JCT
What is the difference between an Employers Agent and a Contract Administrator?
What is a material/non-material breach?
* Non-material – claim damages
What is the Housing, Grants and Regeneration Act?
* Any project over 45 days must have interim payments
What did the update to the Housing grants and regeneration act include?
* If client fails to issue payment notice, contractor can issue default payment notice. (ISG vs Ceevic college)
What contract suite do you have experience in?
The JCT Suite, mainly D&B.
What do you know about NEC?
Both another form of contracts to choose from but I do not have experience in these.
NEC:
- Written in simple language.
Defects correction period is 2 – 3 weeks
- There is no QS.
- There are no provisional sums
- There are options for target cost contracts
- The programme is a contractual document
- Payment is located in three separate sections of the contract as opposed to JCT where it is all found in one - clause 4.
JCT deals with time and money separately with EOTs whereas NEC will deal with both time and money.
What does NEC stand for?
New Engineering contract
What is an EA?
What is a CA?
What is an interim valuation?
The payment process at interim stage of the project, set out at clause 4.7 and the contract particulars refer.
What are the payment timescales for a D&B contract?
This depends on whether you have opted for alternative A or B.
Alternative B is periodic payments, monthly.