What is a contract?
An agreement between 2 or more parties which is intended to be legally enforceable.
What types of Contract are there?
Lump sum / target / reimbursement / remeasurement
Why are they required / relevant for the construction industry?
What is a Letter of Intent?
A document from an employer to a contractor (or from a main contractor to a subcontractor) indicating the employer’s intention to enter into a formal written contract for works described in the letter, and asking the contractor to begin those works before the formal contract is executed.
What elements must be in place in order for a legally binding contract to be created.
certainty as to key terms;
consideration (the ‘price’ paid under the contract in return for performance by the other party of its obligations; and
a mutual intention to enter into a binding legal contract.
What is Quantum Meruit?
Quantum meruit is a judicial policy that allows a party to recover losses in the absence of an agreement or binding contract.
What are the different ways in which a contract can be made?
How is a contract converted from under hand to under deed?
The contract should state somewhere (e.g. in the first line) that it is a deed;
The appropriate signature blocks for deeds should be used.
What is the main legal difference between under hand and under deed?
There is no need for ‘consideration’ in a contract made as a deed (signed by both parties).
The limitation period (the time limit for commencing legal proceedings) is 6 years from the breach of contract in the case of contracts under hand, and 12 years from the breach of contract in the case of deeds.
What are the key elements of a contract executed under hand?
What are the key elements of a contract executed under deed?
What are the key requirements for a contract to be made binding?
What are common contract documents?
a) Conditions of contract and any amendments to standard forms
b) Preliminaries
c) Contract sum analysis
d) Drawings
e) Specifications
f) Existing building information
g) Any contractor’s proposals for CDP work
Who needs to understand the contract?
What project elements to consider when deciding on the most appropriate a form of contract?
What forms of contract are there?
1) JCT (Joint Contracts Tribunal)
2) NEC3 (New Engineering Contract)
3) ICE 7 (Institute of Civil Engineers)
4) GC Works (PACE – Property Advisors to the Civil Estate)
5) FIDIC (International Engineers Federation)
Name the main types of JCT contract
a) Minor works
b) Intermediate
c) Standard building contract
d) Major Projects
e) Design and Build
f) Prime cost contract
g) Measured Term contract
h) Construction Management Agreement
i) Management Contract
j) Framework Agreement
What standard forms of JCT contracts are you aware of?
When would you use JCT Minor Works?
When would you use JCT Intermediate Contract?
When would you use JCT Standard with quantities?
When would you use JCT Standard without quantities?
When would you use JCT Standard with approximate quantities?
When would you use JCT Major Works?
- Generally for clients that have their own in house contractual procedures