NEC Options
Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract
Key updates from NEC3 to NEC4
When would you recommend NEC to a client?
Why did you choose to use an Option A on the DWP expansion programme?
Which NEC ECC poses most and least risk for employer
Option E - contractor reimbursed for actual loss plus fee
Option A - fixed priced contract
How is risk managed in NEC
What is a compensation event
Unforeseen or uncontrollable event that impacts the cost or time needed to complete
Does NEC have relevant events and matters?
No, CE deals with these issues
What happens if contractor notifies a CE 12 weeks after becming aware of the event
What is an Early Warning Notice and when would this be used?
What are the events for a CE
Compensation event timeline
Schedule of cost components in NEC
Costs that can be claimed by the contractor
- People
- Equipment
- Materials
- Charges
- Manufacutre and fabrication
- Design
- Insurance and Bonds
NEC payment timeline (under Y(UK) 2)
NEC payment timeline (without Y(UK) 2)
Clause Y(UK)2 - ensure compliance with UK Housing grants, construction and Regeneration Act 1996
Without Y(UK)2 means payment date is not fixed
How is retention dealt with under the NEC?
How can early contractor involvement happen on NEC
Secondary option X22
How are cost to changes assess on NEC
E.g. Option A uses pre determined people rates included in tender, rather than building them up
Why is NEC favoured by the public sector
Lathem Report
* Client should be core of construction projects
* Industry should move away from its adversarial structure
* NEC uses as its a less advisarial form (Collab) (less disputes)
What are XYZ clauses
X - Pre written option clause
Y - Country specifc, relate to jurisdication
Z - Bespoke / customised clauses (Specific payment mechanisms)
How is completion defined under NEC
All works in WI done by completion date
and
corrected all defects that would have prevented the employer from using the works