3. You are in the Determine Budget process of developing a budget or cost baseline and project funding requirements. All of the following are inputs in this process EXCEPT: A. Work performance data B. Cost management plan C. Activity cost estimates D. Project schedule
Total fund or cost budget = cost baseline + management reserves.
Cost baseline = project cost + contingency reserves
The cost baseline is the project cost plus the contingency reserves, and the cost budget, or how much money the company should have available for the project, is the cost baseline plus the management reserves. The project manager determines, manages, and controls the contingency reserves, which will address the cost impact of the risks remaining during the Plan Risk Responses process. On the other hand, management reserves are funds to cover unforeseen risks or changes to the project. In this case, the cost baseline and the management reserves will be most helpful to calculate the total funding and periodic funding requirements. Funding limit reconciliation is the technique of reconciling the expenditure of funds with the funding limits set for the project. As per the variance between the expenditure of funds and planned limit, the activities can be rescheduled to level out the rate of expenditures.
5. You are in the Determine Budget process of developing a budget or cost baseline and project funding requirements. All of the following are tools & techniques in this process EXCEPT: A. Cost aggregation B. Data analysis C. Funding limit reconciliation D. Performance review
We know SPI = EV/PV or SPI = $202,500/$225,000 = 0.9
11. Your project has a budget of $900,000 and is running well. In the latest earned value report, the team reported that the CPI = 1.1, the SPI = 0.9, and the PV= $600,000. You want to know, from this point on, how much more the project will cost, but could not find it in the report. What will be the estimate to complete, or ETC, be in this case? A. $300,000 B. $327,272 C. $818,181 D. $490,909
13. There were eight potential projects in your organization, and your senior management wanted to select the best project that would meet and exceed the organizational strategic goals and objectives. As your organization has limited resources and time constraints, it developed business cases for these projects and compared the benefits to select the best project. Out of eight projects, management has selected two projects and later on decided to go for Project X, which would yield $250,000 in benefits instead of Project Y, which would yield $200,000. What is the opportunity cost for selecting Project X over Project Y? A. $250,000 B. $200,000 C. –$250,000 D. –$200,000
15. The project manager and the team members have just finished working on the WBS and have almost finalized the project schedule. The project manager is also planning to start working on the project budget. Which document will be used for planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget? A. Earned value management B. Cost baseline C. Cost management plan D. Funding limit reconciliation
17. A project manager is working on a project designed to create an internal website for ITPro Consultancy, LLC that will allow them to schedule the conference room online. While reviewing the status of the project, the project manager found out the EV, AC, and PV (listed in the table below). What are the SPI and CPI? PV EV AC Project 242,200 224,000 140,500 A. 0.925 and 1.59 B. 1.59 and .925 C. 0.919 and 1.77 D. 1.77 and 0.919