How does design-award-build affect the role of the architect during construction?
Architect can act as an impartial interpreter of the contract documents
Which project delivery method allows specifically for the lowest reasonable cost for the project?
Design-award-build
Two major downsides of the design-award-build method.
What potential construction method does construction management open?
Fast-track construction
A construction manager who acts as a contractor assumes what kind of relationship with the owner? And therefore…
Vendor relationship… And therefore he takes Financial responsibility for the construction of the project
Three types of financial responsibility a contractor may take/be paid in
A fixed price structure means that the contractor takes on ____ but that the client cannot…
Financial liability… But the client cannot obtain any savings that might occur from a positive bid climate
Which pricing type allows the construction manager our contractor to charge the owner the actual construction costs of the project plus a negotiated fee?
Cost plus fee
Who is the guaranteed maximum price method best for and why?
Probably the client… Because any cost savings for my positive bed Clement go to the owner rather than the contractor, but the contractor becomes responsible for any bid costs over the guaranteed maximum price.
What are three advantages of using a construction management delivery method?
What is the disadvantage of a CM?
Adds a cost for the CM, and add complexity to the design and construction team
4 advantages of design/build delivery.
4 disadvantages of the design/build delivery method.