Actual Cost
What the project has spent so far
Budget at Completion
What the project budget is.
Planned Value
What the project should be worth.
PV = % planned completion
Earned Value
What the project is worth
EV = % planned completion x BAC
Cost Variance
The difference between earned value and actual cost
CV = EV - AC
Schedule Variance
The difference between earned value and planned value
SV = EV - PV
Cost Performance Index
Shows overall cost efficiency on the project
CPI = EV /AC
Schedule Performance Index
Shows overall schedule adherence
SPI = EV / PV
Estimate at Completion (Standard formula)
Forecast final project costs based on current performance.
Standard formula.
EAC = BAC / CPI
Other note:
as per research and reading, EAC is to forecast scheudle or cost is not very much overruns.
Estimate at Completion (Future work at planned cost formula)
Forecast final project costs based on current performance.
Future work at planned cost formula
EAC = AC + BAC - EV
Other note:
as per research and reading, EAC is to forecast scheudle or cost are overruns.
Estimate at Completion (CPI and SPI affect remaider of project)
Forecast final project costs based on current performance.
EAC = AC + [ (BAC - EV) / (CPI x SPI) ]
Other note:
as per research and reading, EAC is to forecast scheudle or cost are fucked up overruns and worst case scenario.
Estimate at Completion (Initial cost estimates flaws)
Forecast final project costs baed on current performance.
EAC = AC - Estimate for remaider of project
OR
EAC = AC - ETC
Other note:
as per research and reading, EAC is to forecast scheudle or cost are overruns a little bit (not so fucked up).
Estimate to Completion
Product how much more the remaider of the project will cost.
ETC = EAC - AC
To Complete Performance Index (BAC)
Predict likelihood of reaching BAC
Great than 1, harder to complete and meet based on BAC.
Less than 1, easier to complete and meet based on BAC.
TCPI (BAC) = (BAC - EV) / (BAC - AC)
To Complete Performance Index (EAC)
Predict likelihood of reaching EAC
Great than 1, harder to complete and meet based on the EAC.
Less than 1, easier to complete and meet based on the EAC.
TCPI (EAC) = (BAC - EV) / (EAC - AC)
Variance at Completion (VAC)
Projection of being over or under budget based on the current performance.
VAC = BAC - EAC
Code: Please Eat Carl’s Sugar Candy SEE The Tuffy Violin.
Please = PV Eat = EV Carl's = CV Sugar = SV Candy = CPI S = SPI E = EAC E = ETC The = TCPI (BAC) Tuffy = TCPI (EAC) Violin = VAC