Rough order of magnitude
Simple, early estimate. Range of variance is -25% to +75% for the project completion.
Budget estimate
Early planning estimate and/or top down approach. Range of variance is -10% to +25% for the project completion.
Definitive estimate
Most accurate estimate, but takes longest to complete; use bottom-up approach. Range of variance is -5% to +10% for the project completion.
Bottom up approach
Requires a WBS and account for each work package
Analogues approach
Creates an analogy between project; also known as a top-down estimate.
Parametric
Uses a parameter, cost per ton, cost per unit for the estimate.