what is the definition of Earned Value Management
Earned value management (EVM) is a project control process based on a structured approach to planning, cost collection and performance measurement. It facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan for performance measurement.”
why is earned value needed
Most organisations already have methods in place to measure actual expenditure against planned expenditure. This analysis only provides part of the story. EVM adds a third dimension, the value of work performed to date (i.e. Earned Value). Another way to think of Earned Value is “useful work done”
what 8 elements need to be in place for EVM to be effectively applied
what does the success of EVM relies on
EVM relies on both the accuracy of the baseline input and the accuracy of the progress measurement data provided.
what 6 questions regarding present project status does EVM give insight into
what 6 indicators does EVM provide on future project performance
what 4 components are identified by EVM either in planning or through monitoring and control:
what is the calculation used to determine Earned Value - EV
EV =
% Complete x Budget
Value of work performed expressed in terms of budget assigned to that work. Also known as:
BCWP – Budgeted Cost of Work Performed
what is the calculation used to determine Cost Variance - CV
CV = EV – AC
Difference between the value of the work performed and the actual costs incurred. A negative number indicates poor performance whereas a positive number indicates favourable performance.
what is the calculation used to determine Schedule Variance - SV
SV = EV – PC
Difference between the value of the work performed and the planned cost of the work that should have been performed at this point in time.
A negative number indicates poor performance whereas a positive number indicates favourable performance.
what is the calculation used to determine Cost Performance Index - CPI
CPI = EV / AC
Cost efficiency ratio that measures work accomplished against costs incurred at a specific point in time. Number above 1 indicates favourable performance; below 1 indicates poor performance.
what is the calculation used to determine Schedule Performance Index - SPI
SPI = EV / PC
Schedule efficiency ratio that measures work accomplished against work planned at a specific point in time.
Number above 1 indicates favourable performance; below indicates poor performance.
what is the calculation used to determine Estimated Cost at Completion (Cost) - EAC
EAC = BAC / CPI
Projected final cost for the project (also known as the projected outturn cost)
what is the calculation used to determine Estimated Final Duration
(or Estimated Time to Complete) - FD (also known as EACT or ETC)
FD = PD / SPI
Projected final duration for the project
what are 2 of the more commonly used methods of graphical EVM reporting
2. ‘Bull’s-eye’ Charts
what are 5 advantages of EVM
what are 6 disadvantages of EVM