What is retention?
It is a percentage of each interim certificate deducted and retained by the employer from each interim payment to the contractor
What is the purpose of retention?
When is retention released to the contractor?
What is a typical retention percentage under JCT contracts?
Between 3 and 5% depending on the form in use
When would you use JCT and NEC contracts?
What is an NEC contract and why might you use it?
What are the different NEC options?
Option A - Priced contract with activity schedule
Option B - Priced contract with bill of quantities
Option C - Target Contract with activity schedule
Options D - Target Contract with bill of quantities
Option E - Cost reimbursable contract
Option F - Management Contract
What is a collateral warranty?
-They create contractual relationships between the main parties of a contract and an external third party (sub-contractor)
- the contractual relationship would not exist with the party due to privity of contract
What packages would you advise getting a warranty for and why?
Packages that have a high design content and pose a risk to the project
When would you use an intermediate contract?
-Used to bridge the gap between standard and minor works
- less lengthy contract terms than standard and more detailed than minor
- fixed price lump sum
- intermediate with contractors design portion available
Name some contractual mechanisms within the D&B contract
2.3 date of possession; contract particulars; clause 2.3 date when site is given to the contractor, begin construction and proceed to complete on it before completion date
When would you use JCT & NEC Contracts?
Name some difference between the two if you were advising a client on what to use as a proposed form?
What is the format of a JCT contract (standard & D&B)?
What is contained within the contract conditions of a JCT Contract?