When would you use JCT & NEC Contracts?
Name some differences between the two if you were advising a client on what to use as a proposed form?
PALM:
- Programme - unamended JCT not contractual whereas it is in a NEC
- Admin - JCT is administered by the CA/EA whereas in NEC the Project Manager
- Language - JCT contracts use complex legal jargon whereas, NEC plain English
- Money & Time - JCT has relevant events & relevant matters whereas NEC together in compensation events
Can you name the types of NEC Contracts?
Can you name the contract within the JCT suite?
Describe the layout of JCT?
Articles of agreement:
- Recitals
- Articles
- Contract particulars
- Attestation
Conditions:
- Section 1: Definitions and Interpretations
- Section 2: Carrying out the works
- Section 3: Control of the works
- Section 4: Payment
- Section 5: Change
- Section 6: Injury, Damage and Insurance
- Section 7: Assignment, third party rights and collateral warranties
- Section 8: Termination
- Section 9: Settlement of Disputes
Schedules:
- Contractors design submission procedure
- Supplemental provisions
- Insurance Options
- Code of practise
- Third Party rights
- Form of Bonds
- Fluctuation Options
How do you pick which contract to use?
When would you use JCT Standard Building Contract?
When would you use an Intermediate contract?
When would you use Minor Works Contract?
Whats the difference between minor works and intermediate?
What’s the difference between intermediate and standard building contract?
SBC has 3% retention
ICD has 5% retention
ICD has no provision for third party rights
ICD has no provision for retention bonds
When would you use JCT Design and Build Contract?
Name some contractual mechanisms within the D&B contract?
Do you have Collateral warranties in a D&B contract?
Yes
What are Collateral Warranties?
Who may want a collateral warranty?
How are defects addressed in JCT contract?
What is a change called in a JCT Design and Build Contract?
What constitutes a change in JCT SBC?
What is a change called in a JCT Standard Building Contract?
What are the valuation rules?
There are a variety of valuation rules, the main ones are:
- Using rates within the priced document (CSA) - when works are of a similar ‘character’ to the contract documents
- Value at fair rates and prices - when works are not of a similar nature
- Dayworks - when works cannot be properly valued by measurement
- Changes to the CDP works -
What are dayworks?
NRM2 defines dayworks as - ‘the method of valuing work on the basis of time spent by the contractors workpeople, the materials used and the plant employed’.
What happens at practical completion?
What is sectional completion?