During the ______ of the project, the owner selects a party (Contractor) to undertake his/her project.
procurement phase
The selection process is based on pre-set criteria mandated by ___________________________.
statute (Public works) or established by the private owner or his/her agent (A/E or CM)
Project Award methods
Competitive bidding, negotiation, Direct Assignment
Open or selective [can be used by both public or private owners]
Competitive bidding:
Mostly used in private projects, very seldom used in publicly owned or financed projects.
Negotiation:
Mostly used in private projects.
Direct Assignment:
Competitive bidding
Negotiated Bidding
Advantages of Competitive Bidding
Disadvantages of Competitive Bidding
Advantages of negotiated bidding
Disadvantages of negotiated bidding
Elements of the Bid
Invitation to bid includes these things
Elements of the Bid
IFB includes these things
IFB is usually prepared by ________, and the same party will be responsible for distribution, explanation, corrections, collection, review, evaluation, and recommendation to the owner.
A/E or CM
Preparer of the IFB, should expect the offset values to be ______ (depending on preparer’s experience, and availability and accuracy of information)
+/- 10 – 20 %
Bid Tabulation
Project team building three steps
One of the primary benefits of this partnering process is that it increases the perception of all parties to the contract that they have the same common goals
Partnering as a vehicle for team building
Partnering as a Vehicle for Team Building
Formalizing the Partnering Process
Benefits of Working as a Project Team