Claims
If not resolved amicably, a claim can become a _____.
dispute
Generally, ____________ usually result in claims.
Contract document modifications
Three sources of claims may occur on a project.
A contractor prepares pricing based on the _________ and other factors that are reasonably foreseeable at the time.
procurement documents
If, during the course of the project, the contractor encounters conditions contrary to those stipulated or inferred in the contract documents, a ____ may be initiated.
claim
Change conditions include:
The contractor is required to provide clear documentation that a changed condition actually was not ________ at the time of pricing and resulted in demonstrable damages.
not foresseable
Claims resulting from changed conditions may also be submitted by the _______ on behalf of the contractor’s subcontractors and suppliers.
contractor
In claims involving breach of contract, the contractor must __________________ by the other party.
document nonperformance
Two types of claims relating to breach of contract are .
2. claims for improper or ineffective construction contract administration
Why would the Owner make a Claim?
Ineffective management and/or control of the work by the contractor resulting in added costs for:
Owner’s claims
An example could be the excessive settlement or cracking of an existing building foundation where an adjacent excavation caused unstable soil conditions to occur.
third party claim
Under the provisions of ________, the contractor agrees to indemnify the owner and A/E against all thirdparty claims resulting from the contractor’s performance of work on the project.
AIA Document A201 and EJCDC C-700
Third party claims may not require a privity of contracts, and are therefore often filed as ___.
torts
Generally, _____ arise from construction activities that affect the interests of others in areas adjacent to or in the vicinity of the project.
third-party claims
Injury or death to persons and property damage claims are high on the list in terms of frequency and severity.
Third-party claims
Standard forms of contracts usually contain ______ reserving the rights and identify the responsibilities of the owner, contractor, and A/E.
provisions
general or prime contractor (first tier)
effect of the claim
_________ identify a structured methodology for initiating and resolving claims expeditiously.
AIA general conditions
Standard general conditions establish the A/E as the _______ of the contract documents.
impartial interpreter