How is a road or pavement constructed?
What are the sustainable environmental assessments to certify a project?
What is the difference between rigid and flexible paving?
Difference between green roof and blue roof?
What is the difference between artificial stone paving and York stone paving?
How did you estimate the cost of the HVM’s?
I spoke to a specialist supplier who provided the associated costs of the different mitigation methods, this included installation costs.
How do you install palisade fencing?
Dig a hole for each fence post, add gravel and pour concrete in the hole, insert the post and ensure level and let it set at least a day.
How do you install Heras fencing?
Poles are fitted securely into concrete bracing blocks and connected using anti-tamper couplers.
What was the design and cost of the proprietary mat system?
What things does a contractor need to consider when excavating?
What is a retaining wall?
A retaining wall is a structure designed and constructed to resist the lateral pressure of soil, when there is a desired change in ground elevation that exceeds the angle of repose of the soil.
Name some types of foundation?
What are the different types of construction methods for bridges?
What are the different types of construction methods for tunnels?
What sort of temp drainage solutions are there?
What types of fencing are there? Why did you advise heras?
What are typical surveys that would be required for a construction project?
Services
What are the main suites of construction contract?
Advantages of FIDIC contract?
Internationally recognized
4 main options, Lump sum, design and build, short form and turnkey which NEC3 doesn’t offer
Please talk me through an example from your experience of a situation where you have prepared a report which recommends the appropriate form of contract to be adopted?
• Option A – Fixed price with activity schedule
Lowest risk
more price certainty
pay a premium for risk
• Option B – Fixed price with Bill of quantities –
Weren’t defined quantities in scope
defined scope but not defined quantities
Design and build so incentivize over design
• Option E – Cost Reimbursable
low cost certainty - usually used when scope isn’t clear
Explain how you have advised on the appropriateness and implications of proposed contractual mechanisms?
Whilst on Beckton depot enabling works package 2 I advised the use of the additional clauses
• X4 - Parent company guarantee
• X7 - Delay damages
• X16 - Retention
i also considered inflation but project not long enough
I was aware that the contractor was a subsidiary of a larger company so I advised that a parent company guarantee would offer insurance against insolvency of the contractor we were in contract with.
What is a Parent Company Guarantee?
An arrangement where the contractual performance of one company in a corporate group is underwritten by the other members of that corporate group.
What are the contractual benefits of a Framework over other procurement options?
Explain how you have managed a compensation event in a project you worked on?
Beckton depot enabling works:
Early Warning Notification – protected species
Risk reduction meeting – discuss mitigation
NCE raised – assessed for entitlement – Within 8 weeks
Detailed as employers’ risk in contract data 2
Gained necessary internal approvals
Accepted NCE – Employer reply’s in 1 week
No reply Contractor notifies after 1 week
If no decision is made 2 weeks after reminder then treated as accepted
Awaited quotation - 3 weeks to submit a quotation
Assessed Quotation - 2 weeks to reply to quotation
If no reply contractor notifies, if PM does not reply then after 2 weeks after reminder quote accepted