How did you normalize bids on Beckton depot enabling works?
How did you create the tender documentation for the bidders to value?
How have you negotiated and agreed the valuation of construction works at various stages of a project such as contract sum, construction and final account?
On Beckton depot enabling works it was decided by the client that the mains foul water connection was no longer needed.
The contractor priced the work in the activity schedule at £110k as part of the tender.
The PM assumed they would receive back the value from the activity schedule price.
I advised the PM it would not be a case of removing the activity and returning the cost.
Under NEC3 ECC option A the cost would should be calculated on I built up a price from forecasted defined cost and the costs already incurred.
I advised that we Issue a PMI for the contractor to provide a quotation for the descope based on:
(i) the Defined Cost of the work already done
(ii) the forecast Defined Cost of the work not yet
done
(iii) the resulting fee (fee percentage applied to
the amount of Actual Cost covering specific
costs, mainly head office overheads and
profit).
How have you advised on appropriate methods of measurement and costing?
…
Describe advice given to a client in the valuation of variations, what was your advice? How did you arrive at this decision? why was it better than alternatives?
…
What is the Civil Engineering Standard Method of Measurement?
CESMM – has been well established for over 20 years as the standard for the preparation of bills of quantities in civil engineering work
When was the latest edition of the CESMM?
Volume 4 revised in 2019 published by ICE
How is the CESMM categorised?
26 classes - A-Z – Ground investigation, site clearance, earthworks, pipework, roads..etc
How would you advise your client on dealing with an error that was contained within a bid?
On identification of the error I would advise the client that…
What is the purpose of the RICS Code of Measuring Practice?
Provides precise definitions to permit the accurate and consistent measurement of buildings
What methods can be used to form an order of cost estimate?
What is an elemental cost analysis?
Is a full appraisal of cost involved in previously constructed buildings and is aimed mainly at providing reliable information that will assist in accurately estimating the cost of future buildings. It provides a product-based cost model providing data which initial elemental estimates and elemental cost plans can be based on.
What are preliminaries?
Are items which cannot be allocated to a specific element, sub-element or component. Main contractor’s preliminaries include the main contractor’s costs associated with management and staff, site establishment, temporary services, security, safety and environmental protection, control and protection, bonds, guarantees and warranties.
What are enabling works?
Enabling works are the preparation of a site in readiness for the first stage of development. Examples include installing perimeter fencing, carrying out ground clearance, building access routes and putting up safety signage. Enabling works may also include preliminary construction work, such as groundworks.
What are facilitating works?
Facilitating works is a term used to describe specialist works which, normally, need to be completed before any building works can commence (e.g. demolition works, works involving the removal of hazardous and deleterious materials, and soil stabilization
What is defined cost?
Broadly speaking, Defined Costs are the actual costs incurred by the Contractor on the Works minus retention and any costs which would fall within the overheads covered in the Fee
What are disallowed costs?
Disallowed Costs are those which the contractor has incurred, but for which the employer does not have to pay. This could include costs which cannot be justified, those which should never have been paid to a subcontractor or supplier, or those incurred because the contractor did not follow certain stated procedures
What is a schedule of cost components?
The Schedule of Cost Components contains rules for the reimbursement of people employed and not employed within the Working Areas.
What is a bill of quantity?
A bill of quantities (commonly known as BOQ or BQ) is a document prepared by a quantity surveyor or cost consultant to define the quality and quantity of works required to be carried out by the main contractor to complete a project.
What is the black book?
The ‘Black Book’ is a suite of guidance notes that define good technical standards for quantity surveying and construction professional.
Talk me through how you would measure concrete foundations.
For piles the pile mat would need to be measured in m2. A cost for the piling plant and moving the piling rig would need to be factored in and measured by nr. The pile details would need to include diameter (mm) and depth of piles (m) and measured in nr. The disposal of excavated material would need to be cost and measures in m3. Cutting off tops of the pile would need to be measured by nr.
What are the ways of valuing change?
What are the benefits of having a standard method of measurement?
1) Provides structure for information
2) Defines units of measurement for different items (m, m2, m3, t)
3) Provides rules as to what is included within each item
4) Defines terms used to avoid disputes
5) Allows familiarity to development so measurement becomes quicker and easier
6) Provides clear system of structuring other project information
1) Provides structure for information
2) Defines units of measurement for different items (m, m2, m3, t)
3) Provides rules as to what is included within each item
4) Defines terms used to avoid disputes
5) Allows familiarity to development so measurement becomes quicker and easier
6) Provides clear system of structuring other project information
What are the different methods of measurement for a Cost Estimate?
1) Functional Unit
2) Floor Area
3) Elemental
4) Approximate Quantities
5) Bill of Quantities