What is the primary role of a project manager in the delivery of a construction project?
How do you communicate with stakeholders?
What are some way you make sure the project is delivered on time and within budget?
Please explain why it is important to follow the defined project stages?
Adhering to the defined project stages ensures the project is carried out in a structured, organised and logical sequence. Typical defined project stages would include:-
What is ISO9001?
How would you implement a document control Process?
Why is document control important? What happens if not?
Improves efficiency through standardization
Important for security
Ensures the team Is all working from the same information
Important for dispute resolution
What techniques do you adopt to control the time and cost implications of the project?
What do you understand by the term VE?
Value Engineering is an organised approach aimed at providing the necessary functions at the lowest cost, without detrimental effects to Quality, reliability, performance or delivery.
What do you understand by the term VM?
How did you assess whether the client’s intended “light touch” refurbishment would meet market standards?
How did you manage the client’s expectations when your team’s findings contradicted their initial intentions (Jewsons)?
I made sure the reasons that the light touch would not work along side the solutions were presented to the client.
What is the Building Safety Act?
Why did you recommend the architect take the BRPD initially, with responsibility later passing to the contractor?
Why did you advise the client not to progress until the BRPD was appointed?
Because it is a legal requirement under the Building Safety act.
Why did you recommend to switch from single stage to two stage? / Why wasn’t the initial recommendation 2 stage?
How did you manage the performance of the team?
How do you monitor risk?
-Risk register.
How is risk calculated in the risk register?
-likelihood x impact.
What document could help establish roles and communication during a project?
RACI Matrix
What is within a construction contract to deal with regulatory changes and when they occur?
Base date.
- If it become apparent that the ER’s/CP’s don’t comply with legislation the parties shall immediately give
the other notice specifying the divergence; and the Contractor shall notify the Employer of his proposed
amendment for removing it. With the Employer’s consent, the Contractor shall entirely at his own cost,
complete the design and construction of the Works in accordance with the amendment and the
Employer shall note the amendment on the Contract Documents.
-if it is new legislation comes into effect after the base date then this is treated as a change.
How do you communicate risks to the project team
-maintaining a live risk register shared regularly with the team.
-could have a risk communication plan setting out the process for dealing with risk and how this should
be reported by team members. May include meetings, workshops.
What risks did you highlight with the client when switching from single stage to two stage?
-There would be a delay in cost certainty as the final contract sum would not be agreed until the second stage
-Once a contractor is engaged in Stage 1, the client may have reduced leverage in negotiating the final contract terms, especially if market options are limited.
-Scope Creep: Without tight control, the design may evolve significantly during Stage 1, potentially increasing costs and complexity.
What is a deemed change?
Deemed changes or variations are also known as necessary changes. In the JCT Standard
Form of Building Contract, for example, if there are changes to the statutory requirements
after the base date, the contractor is obliged to alter its work to comply with the change.