What are the main procurement routes?
Traditional & General Contracting.
Design and Build.
Management Contracting.
Construction management
What is a procurement strategy?
What is typically included in a tender?
What is the form of tender?
A preprinted formal statement in which the tenderer fills in the blank spaces.
The tenderer provides their name, address and the sum of money for which they offer to carry out the works.
What are the employer’s requirements?
How do you analyse a tender return?
Tender Evaluation:
* Tender returns checked for compliance with the invitation to tender.
* Arithmetical checks carried out on cost components.
* Any non-compliant tenders treated in accordance with the conditions outlined in the Invitation to Tender.
* All tenders aligned on a like for like basis and compared with each other and the pre-tender estimate.
* Analysis undertaken of resource levels committed by each contractor and on the merits of the team proposed.
Interview/scoring
* Post-tender interviews carried out with short listed tenderers.
* Tenders scored against the pre-determined selection criteria.
Tender Recommendation Report prepared and presented to client, including:
* Tender history.
* Summary of tender returns.
* Aligned tenders.
* Scoring of tenders against technical and commercial criteria
* Recommendation on what tender represents overall best value for money.
* Outline of future actions and contracting approach.
What Contract types / procurement routes are you aware of?
** Traditional**
* Design & Construction completed separately
* Appropriate for complex, bespoke projects – high quality guarantee
* Client has high input into desig
* Can be done with / without quantities
* Completed design = cost certainty
* Design risk lies with client; Construction risk lies with Contractor
* Cons: slow start on site, can lead to adverse relationship
Design & Build
* Design & Construction completed by Contractor (Contractor’s Proposals produced in response to the Employer’s Requirements)
* Overlap in Design & Construction = quicker start on site
* Risk almost entirely with Contractor.
* Appropriate for simple, repetitive nature projects
* Lump sum contract = cost certainty
* Buildability input from the Contractor
* Cons: Low quality guarantee as contractor favours buildability & cost savings rather than aesthetics.
Client doesn’t have control over design & changes to ERs can be costly
**Managing Contracting **
* Management Contractor advisory & co-ordination role – breakdown of work packages, sequencing etc
* Management Contractor doesn’t complete any works; only co-ordinates
* MC contractually linked to sub-cons
* Fast programme as work packages can happen concurrently; individual packages can start as soon as design is signed off.
* Low cost certainty as final cost not known until last package is let
Construction Management
* Client contractually linked to sub-contractors.
* Fast programme; individual packages let as soon as signed off.
* Must be experienced client who is aware of their role and associated risks.
* Client control over time & quality; low cost certainty
How did you decide on the appropriate tender period programme?
How did you conduct tender analysis?
What would you do if a tender was returned late?
How did you have tenders returned?
How did you ensure tenders were fair?
If an extension is granted then this extension must be given to all contractors
Any tender queries raised are answered back to all tendering contractors and not just
those that asked the question.
What if further information is obtained after the tender has been released?
A tender addendum would be issued (e.g. if a tenderer asks for the release of a particular survey that is mentioned but is not included in the contract information). If a tender addendum is required then it should be issued as a soon as possible. As much information as possible should be included in a single addendum rather than issuing too many
What is the advantage of tender interviews?
What is traditional procurement?
The design is completed by the client’s design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified.
How does it work?
(traditional procurement)
The contractor takes responsibility and financial risk for the construction of the works to the design produced by the client’s design team for the contract sum within the contract period.
The client takes the responsibility and risk for the design and design team performance.
When might a traditonal route be appropriate?
What are the advantages of traditional procurement?
What are the disadvantages? (of traditional procurement)
What is design and build?
Where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employer’s requirements.
How does it work? (design and build)
The employer gives the tenderers the ‘Employer’s Requirements’ and the contractors responds with the ‘Contractor’s Proposals’, which include the price for the works.
When might it be appropriate? (design and build)
What are the advantages of design and build?
What are the disadvantages? (of design and build)