A. Risk management plan
B. Cost management plan
C. Quality management plan
D. Schedule management plan
1. C PMBOK Guide - The inputs to the perform quantitative risk analysis process include: - Risk management plan - Cost management plan - Schedule management plan - Risk register - Enterprise environmental factors - Organizational process assets
A. Scope baseline
B. Enterprise environmental factors
C. Schedule management plan
D. Risk register
2. A PMBOK - The inputs to the perform quantitative risk analysis process include: - Risk management plan - Cost management plan - Schedule management plan - Risk register - Enterprise environmental factors - Organizational process assets
A. Human resource management plan
B. Scope management plan
C. Quality management plan
D. Organizational process assets
3. D PMBOK Guide - The inputs to the perform quantitative risk analysis process include: - Risk management plan - Cost management plan - Schedule management plan - Risk register - Enterprise environmental factors - Organizational process assets
A. SWOT analysis
B. Data gathering and representation techniques
C. Quantitative risk analysis and modeling techniques
D. Expert judgment
A. Data gathering and representation techniques
B. Empirical data analysis
C. Qualitative risk analysis and modeling techniques
D. All of the above are tools and techniques used in the perform quantitative risk analysis
A. Project document updates
B. Risk register updates
C. Project management plan updates
D. Risk management plan updates
PMBOK Guide - The output to the perform quantitative risk analysis process is project document updates
A. Make use of the Delphi Technique
B. Make use of Monte Carlo Analysis
C. Make use collaboration software
D. Apply Critical Chain Modeling
A. Involve other stakeholders
B. Use a Monte Carlo simulation
C. Mitigate the risks
D. The overall risk ranking for the project
A. Get an indication of the risk involved in a project
B. Simulate the order in which activities occur
C. Estimate an activity’s length
D. Measure project risk level
A. U.S. $1,164
B. U.S. $1,179
C. U.S. $1,191
D. U.S. $1,199
A. U.S. $7,584
B. U.S. $7,610
C. U.S. $7,696
D. U.S. $7,713
A. U.S. $5,776
B. U.S. $5,820
C. U.S. $5,901
D. U.S. $6,030
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
A. U.S. $60,700
B. U.S. $27,500
C. U.S. $33,200
D. U.S. $51,600
A. Project A
B. Project B
C. Both Project A & B offer the same valuation
D. There is not enough information to determine
A. U.S. $6,480
B. U.S. -$3,050
C. U.S. $3,200
D. U.S. -$3,430
A. Project A
B. Project B
C. Both Project A & B offer the same valuation
D. There is not enough information to determine
A. U.S. $34,250
B. U.S. $34,700
C. U.S. $68,950
D. U.S. $68,525