A. Organizational process assets updates
B. Change requests
C. Risk register
D. Project document updates
1. C PMBOK Guide - The inputs to the control risks process include: - Project management plan - Risk register - Work performance data - Work performance reports
A. Risk register
B. Project management plan
C. Enterprise environmental factors
D. Work performance data
2. C PMBOK Guide - The inputs to the control risks process include: - Project management plan - Risk register - Work performance data - Work performance reports
A. Project management plan
B. Organizational process assets
C. Approved change requests
D. Project documents
3. A PMBOK Guide - The inputs to the control risks process include: - Project management plan - Risk register - Work performance data - Work performance reports
A. Risk reassessments
B. Variance and trend analysis
C. Reserve analysis
D. Change request analysis
PMBOK Guide - The tools and techniques used in the control risks include:
A. Risk urgency assessment
B. Risk audits
C. Meetings
D. Technical performance measurement
5. A PMBOK Guide - The tools and techniques used in the control risks include: - Risk reassessment - Risk audits - Variance and trend analysis - Technical performance measurement - Reserve analysis - Meetings
A. Risk urgency assessments
B. Meetings
C. Expert judgment
D. SWOT analysis
6. B PMBOK Guide - The tools and techniques used in the control risks include: - Risk reassessment - Risk audits - Variance and trend analysis - Technical performance measurement - Reserve analysis - Meetings
A. Work performance information
B. Change requests
C. Risk management plan updates
D. Project document updates
7. C PMBOK Guide - The outputs to the control risks process include: - Work performance information - Change requests - Project management plan updates - Project document updates - Organizational process assets updates
A. Organizational process asset updates
B. Project management plan updates
C. Project document updates
D. Risk probability and impact assessment updates
8. D PMBOK Guide - The outputs to the control risks process include: - Work performance information - Change requests - Project management plan updates - Project document updates - Organizational process assets updates
A. Project document updates
B. Risk probability and impact assessment updates
C. Risk management plan updates
D. Communications management plan updates
9. A PMBOK Guide - The outputs to the control risks process include: - Work performance information - Change requests - Project management plan updates - Project document updates - Organizational process assets updates
A. Control risks
B. Plan risk responses
C. Identify risks
D. Quantitative risk analysis
Workarounds, by definition, are responses created for risks not included in the risk register.
A. Inform the project stakeholders
B. Look for secondary risks
C. Exam the identify risks process for flaws
D. Create a workaround