Rounds for Non-Class Switchgear Room?
Fast Bus Transfer Occurs When…
NBN-S01/S02 Fast Bus Transfer When…
Red Light Out on Breaker Means?
How do you Verify All Grounds are Removed?
Which batteries/battery chargers can supply NKN-M45/M46?
- NKN-M46 can have EF or F charger suppling it
Describe how to shift battery chargers
- Parallel the chargers together then remove the first charger by opening the DC output and AC input breakers
Describe and explain the Light Indicators on a 4160 Breaker
Red: breaker closed with continuity through trip coil
Green: breaker open and racked in
Bright Green: breaker tripped on a fault or is in TEST position
White: 86 Lockout is reset
Clear: closing springs charged
What is the procedure for relay resetting? Describe main requirements
What equipment is affected by a loss of normal power to NKN-M46?
On a loss of normal power to NKN-M46, which 2 pumps should be last to turn off?
EBOP
ELOP
What is the difference between a soft and hard ground?
Hard Ground = < 3000 ohms
Soft Ground = > 3000 ohms
< 35,000 ohms
What is the procedure for minimizing breaker damage while racking?
01DP-0IS13 Electrical Safe Work Practices
What is the source of control power for the RCPs and CW pumps?
CW A and B – NKND41
CW C and D – NKND42
RCPs control power – NKND44
How do you Reset Thermal Overloads?
On MCC’s, there will be a black reset button on the front that you will press
Kirk Key interlock
NAN-S01/s02 supplies three load centers on one single breaker
On the load center itself, there is a disconnect. The B2 feeder breaker needs to be open and then a key that is in the breaker can be removed which locks the breaker open. The key can be put into the disconnect door to manually open the disconnect stabs
The aux and main stabs need to all come out ensuring the 13.8 kV is isolated from the load center to remove one load center from the others instead taking out all three load centers on the NAN breaker
OE on kirk key is the aux stab not coming apart on our SWYD load centers NGN-L43 L44
NKN D panel Locations
NKND41 – turb 100’
NKND42 – aux 100’
NKND43 Turb 100’
NKND44 – in M46
NKND45 – in SSR room
NKND19 – chlorinator room cooling tower
NNN D panel Locations
NNN-D11 and D12 : Control bldg. 120’
NNND15 – Turbine 100’
NNND16 – Aux 120’
Loads on NAN-S01
RCP ‘A’ & ‘C’
CWP ‘A’ & ‘B’
3 NG Load Centers
NBN-S01 via Normal Service
XFMR NBN-X01
Loads on NAN-S02
RCP ‘B’ & ‘D’
CWP ‘C’ & ‘D’
3 NG Load Centers
NBN-S02 via Normal
Service XFMR NBN-X02
Loads on NBN-S01
Loads on NBN-S02
Loads on NKN-M45
Loads on NKN-M46