What is Procurement?
The process of acquiring goods, works or services.
What are the main 3 factors when considering a procurement route?
Client objectives
Name some Procurement options
Traditional Design and Build Construction Management Management Contracting Framework Agreements
A brief explanation of Traditional Procurement
The client engages the architect/design team and contractor directly
A brief explanation of Design & Build Procurement
The client engages the contractor who designs and builds
A brief explanation of Construction Management Procurement
The construction manager is employed to arrange trade contracts and monitors them
A brief explanation of Management Contracting Procurement
The contractor performs the role of managing the works contractors who carry out the works
A brief explanation of Framework Agreements
A template contract is agreed for a series of projects
Name some tendering processes
Single Stage Tendering - bid for whole construction work. Usual on traditional route. RIBA after stage 4 tech design.
Two Stage Tendering - tender based on bid quality, then joins design team -usual on D&B route. RIBA stage 2 concept design
Negotiated Tendering - single stage 1 contractor. Not permitted by Public Proc. RIBA stage 2 concept design
A brief explanation of Single Stage Tendering
Multiple contractors tender through one single tender process
A brief explanation of Two Stage Tendering
The contractor is selected for the 1st stage on the basis of limited scope.
The 2nd stage full price is negotiated through open book tendering
A brief explanation of Negotiated Tendering
Where the contract is negotiated with a preferred contractor or contractors.
What is novation
A process where the contractural rights & obligations are transferred from party to another new 3rd party.
What is tendering
The bidding process to obtain and price, also to appoint a contractor
How does procurement through a framework work?
Framework fulfils obligations of public procurement rules. Framework provider vets contractors to allow them onto framework. Can allocate by
How did Brexit change public procurement?
The Public Procurement (Amendment etc.) (EU Exit) Regulations 2020
OJEU replace with ‘find a tender’
What is the Public Contract Regulations 2015?
What are the current public procurement thresholds?
For central gov:
Supply, services and design contracts - £122,976
Works contracts £4,733,252
Special and other services £663,540
What public procurement frameworks are available?
What re the benefits of a procurement framework?
What are pre-qualification procedures?
How are selection criteria used?
Has RICS issued guidance?
Yes, Tendering Strategies guidance document
Procurement of Facility Management
What is the difference between tendering and procurement
Procurement - overall act of obtaining services
Tendering - phase in procurement (bidding and appointment)