Describe your tendering process.
I prepared tender documents, analysed returns, identified errors (e.g. abnormally low pricing), and followed JCT Tendering Practice Note guidance to ensure fairness.
How do you deal with tender errors?
At Shear’s Way, I followed Alternative Provision 2, allowing the contractor to confirm or correct the error, ensuring transparency.
Talk me through how you would procure a project from start to finish.
A (strong structure):
• Understand client objectives (cost, programme, risk)
• Recommend procurement route (e.g. Traditional, Design & Build)
• Consider tender approach (single-stage vs two-stage)
• Prepare tender documentation
• Issue tenders and manage queries
• Analyse returns
• Advise client and appoint contractor
👉 Top-tier line:
“I would also consider whether a single-stage or two-stage tender is appropriate depending on design development and programme constraints.”
How do you decide which procurement route and tendering approach to use?
Based on:
• level of design completion
• programme requirements
• cost certainty needed
• risk allocation
👉 Example:
• Single-stage where design is complete and cost certainty is key
• Two-stage where design is developing and early contractor input is beneficial
What is the difference between single-stage and two-stage tendering?
• Single-stage: full competitive tender based on complete design → strong cost certainty
• Two-stage: early contractor appointment → final price agreed later → better for programme and buildability
When would you recommend two-stage tendering?
Where:
• programme is critical
• design is incomplete
• contractor input is needed early
What are the risks of two-stage tendering?
• reduced competition at Stage 2
• cost escalation
• reliance on contractor pricing
• need for strong cost control
How would you manage those risks?
• clear scope definition
• benchmarking costs
• transparent pricing
• strong commercial control
You receive three tenders — one is significantly cheaper. What do you do?
• identify as abnormally low
• query contractor
• follow JCT guidance
• allow correction/confirmation
• advise client on risk
The client still wants to appoint the cheapest contractor — what do you do?
• advise on risks (quality, claims, insolvency)
• provide comparison
• document advice
A contractor submits a late tender but is highly capable — what do you do?
• maintain fairness → reject
• explain risk of undermining process
What makes a good tender package?
• clear drawings and specification
• defined scope
• no ambiguity
• Pre-Construction Information included
How do you ensure tenders are comparable?
• same information issued
• structured pricing documents
• identify exclusions
• normalise returns
Contractors are asking lots of questions — what does this indicate?
Potential lack of clarity in tender documents → risk of inconsistencies and disputes
Would you negotiate after tender?
Yes — but carefully:
• clarify scope
• adjust pricing
• maintain fairness
What is the difference between competitive and negotiated tendering?
• competitive = multiple contractors
• negotiated = single contractor
You issued incorrect information during tender — what do you do?
• issue clarification to all
• extend deadline if needed
• maintain fairness
Client wants speed AND cost certainty — what do you advise?
Explain trade-off:
• Single-stage → cost certainty
• Two-stage → programme advantage
👉 Then recommend based on priority
How do you ensure fairness in the tender process?
• same info to all
• equal deadlines
• transparent process
• no preferential treatment
What is the biggest risk in procurement?
Selecting the wrong procurement route or contractor.
How do you demonstrate value to the client in procurement?
• identify risks
• analyse tenders properly
• advise beyond cost
• ensure best value outcome
How does procurement impact the rest of the project?
It sets the framework for:
• risk allocation
• contract administration
• cost and programme control