Procurement & Tendering Flashcards

(22 cards)

1
Q

Describe your tendering process.

A

I prepared tender documents, analysed returns, identified errors (e.g. abnormally low pricing), and followed JCT Tendering Practice Note guidance to ensure fairness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you deal with tender errors?

A

At Shear’s Way, I followed Alternative Provision 2, allowing the contractor to confirm or correct the error, ensuring transparency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk me through how you would procure a project from start to finish.

A

A (strong structure):
• Understand client objectives (cost, programme, risk)
• Recommend procurement route (e.g. Traditional, Design & Build)
• Consider tender approach (single-stage vs two-stage)
• Prepare tender documentation
• Issue tenders and manage queries
• Analyse returns
• Advise client and appoint contractor

👉 Top-tier line:
“I would also consider whether a single-stage or two-stage tender is appropriate depending on design development and programme constraints.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you decide which procurement route and tendering approach to use?

A

Based on:
• level of design completion
• programme requirements
• cost certainty needed
• risk allocation

👉 Example:
• Single-stage where design is complete and cost certainty is key
• Two-stage where design is developing and early contractor input is beneficial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between single-stage and two-stage tendering?

A

• Single-stage: full competitive tender based on complete design → strong cost certainty
• Two-stage: early contractor appointment → final price agreed later → better for programme and buildability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you recommend two-stage tendering?

A

Where:
• programme is critical
• design is incomplete
• contractor input is needed early

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the risks of two-stage tendering?

A

• reduced competition at Stage 2
• cost escalation
• reliance on contractor pricing
• need for strong cost control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you manage those risks?

A

• clear scope definition
• benchmarking costs
• transparent pricing
• strong commercial control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You receive three tenders — one is significantly cheaper. What do you do?

A

• identify as abnormally low
• query contractor
• follow JCT guidance
• allow correction/confirmation
• advise client on risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The client still wants to appoint the cheapest contractor — what do you do?

A

• advise on risks (quality, claims, insolvency)
• provide comparison
• document advice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A contractor submits a late tender but is highly capable — what do you do?

A

• maintain fairness → reject
• explain risk of undermining process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What makes a good tender package?

A

• clear drawings and specification
• defined scope
• no ambiguity
• Pre-Construction Information included

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you ensure tenders are comparable?

A

• same information issued
• structured pricing documents
• identify exclusions
• normalise returns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contractors are asking lots of questions — what does this indicate?

A

Potential lack of clarity in tender documents → risk of inconsistencies and disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Would you negotiate after tender?

A

Yes — but carefully:
• clarify scope
• adjust pricing
• maintain fairness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between competitive and negotiated tendering?

A

• competitive = multiple contractors
• negotiated = single contractor

17
Q

You issued incorrect information during tender — what do you do?

A

• issue clarification to all
• extend deadline if needed
• maintain fairness

18
Q

Client wants speed AND cost certainty — what do you advise?

A

Explain trade-off:
• Single-stage → cost certainty
• Two-stage → programme advantage

👉 Then recommend based on priority

19
Q

How do you ensure fairness in the tender process?

A

• same info to all
• equal deadlines
• transparent process
• no preferential treatment

20
Q

What is the biggest risk in procurement?

A

Selecting the wrong procurement route or contractor.

21
Q

How do you demonstrate value to the client in procurement?

A

• identify risks
• analyse tenders properly
• advise beyond cost
• ensure best value outcome

22
Q

How does procurement impact the rest of the project?

A

It sets the framework for:
• risk allocation
• contract administration
• cost and programme control