Project Feasibility Analysis Flashcards

(19 cards)

1
Q

What is value management?

A
  • Involved in looking at the whole management approach to the project to see if there are any ways in which the project can be completed more efficiently or effectively.
  • It is seen as pro active
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is value engineering?

A
  • It is a systematic method aimed at improving value of a project by improving a certain aspect of the design
  • It is seen as reactive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is life cycle costing

A
  • According to RICS, Life Cycle Costing (LCC) is a process that evaluates and models all costs associated with an asset throughout its entire lifespan, from initial capital expenditure through operational and maintenance costs to end-of-life costs, including disposal.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is whole life cycle costing?

A
  • According to RICS, Whole Life Costing (WLC) is a process that covers everything that LCC does but also takes into consideration non construction costs, income and externalities.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between life cycle and whole life cycle costing?

A
  • Life cycle costing looks at a building or asset and the costs from construction/ manufacturing through it’s operation life and maintenance.
  • Whole life cycle costing looks takes all the previously mentioned into consideration plus end of life/ disposal costs, income and externalities.
  • This is defined in the RICS guidance note on LLC and WLC.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you produce a whole life cost assessment?

A
  • My experience producing a WLC has been using a software called One Click LCA that is approved by RICS, however, I am aware of the RICS guidance note on WLC and it includes the following:
  • defining the project’s boundary and life cycle stages
  • calculating embodied and operational carbon
  • assessing replacement and end-of-life impacts
  • RICS NRM classification system for elemental breakdown
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are capital costs?

A
  • Capital costs, or Capital Expenditures (CapEx), are funds a business uses to acquire, upgrade, or maintain long-term assets such as property, plant, and equipment, rather than for day-to-day operating expenses. With regards to LCC these are all relevant costs incurred before the base date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you assess operational and maintenance costs?

A
  • I’d use a Planned Preventative Maintenance (PPM) schedule to systematically identify and budget for future building needs, contrasting it with unplanned, reactive maintenance.
  • Key steps include a detailed inspection, creating a risk-based cost breakdown, using cost data benchmarking tools like BCIS to compare against industry standards, and ensuring the PPM plan is a dynamic document updated with new information and informed by professional advice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the RICS guidance on appraisals?

A
  • RICS guidance on property appraisals is primarily contained within RICS Valuation – Global Standards, commonly known as the “Red Book”.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do the RICS guidance notes say on appraisals?

A
  • The RICS Red Book includes global and UK-specific mandatory standards, best practice guidance, and commentary for <property valuations undertaken by RICS members. It ensures valuers follow the International Valuation Standards (IVS), and covers the minimum content of a valuation report.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Other than LCC and WLC, what else is involved in carrying out an appraisal?

A
  • In my experience I have only carried out LCC and WLC but I am aware that in RICS red book it sets out an appraisal in the following stages:
  • Gross Development Value (GDV) ie the estimated market value of the development
  • Development Costs which include land costs, construction costs, fees etc
  • Developers profit
  • Residual land value
  • Cash flow
  • Sensitivity analysis
  • Assumptions and inputs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What non-financial factors can affect feasibility studies?

A
  • Location and Environmental impact
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an environmental impact assessment?

A
  • It is a statutory process that evaluates the potential significant environmental effects of a construction project before it is approved, with the goal of avoiding, reducing, or offsetting negative impacts.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is an environmental impact assessment carried out?

A
  • Identify any impacts
  • Develop appropriate mitigation methods if required
  • Involve the public
  • Publish environmental statement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What information must be in place to carry out a feasibility estimate?

A
  • Existing Site information
  • Site appraisals
  • Planning permissions and legal approvals
  • Budget and cost analysis
  • Accommodation considerations
  • Servicing strategies
  • Operational and maintenance issues
  • Programme considerations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a discounted cashflow and when would you use it?

A
  • A discounted cash flow (DCF) is a valuation model that estimates a property’s current value by projecting its future net income or cash flow and then discounting that flow to its present value.
  • RICS guidance, DCF is best used to help with investment buy/sell decisions or to value investments where market transactions are scarce or where a rational framework is needed to derive Market Value.
17
Q

Can you explain the key components of a development appraisal?

A
  • Gross Development Value (GDV) ie the estimated market value of the development
  • Development Costs which include land costs, construction costs, fees etc
  • Developers profit
  • Residual land value
  • Cash flow
  • Sensitivity analysis
  • Assumptions and inputs
18
Q

You mentioned conducting life cycle cost exercises for warehouse developments — what elements did you include in your cost model?

A

Elements required in an LCC or WLCC model are:
- Construction costs
- Operational costs such as energy consumption and water consumption
- Maintenance cost such as for the M&E systems
- Occupancy costs
- End of life costs
(WLC)
- Non construction costs (land and fees)
- Income
- Externalities

19
Q

Can you tell me about one of the feasibility projects you were involved in at ISG and some of the value and risk management exercises you undertook?

A

Similarly to my case study project I was given a task of performing a LCC on installing new M&E equipment on a potential asset for a client. This process involved conducting a VM exercise on the potential interventions and also the risks associated with those works and the client owning the asset of the Life Cycle of the building.